Breakup

18.1.3.2 12 mm thick Garjan Ply board ceiling

Considering a panel of 12' x 16'= 192 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Garjan/Jam/local Sal Cost of Garjan wood: (7 x 16' + 9 x 12') x 2" x 1.5"= 4.58 cft Leg -20x 2'-3''x2"x1.5''= 0.94 cft 5.52 cft Add 5% wastage= 0.28 cft = 5.80 cft 5.8 cft 2200 per cft 2200 12760
2 12mm thick Garjan ply board Cost of 12mm thick Garjan ply board 192.00 sft Add 5% wastage= 9.60 sft = 201.60 sft 201.6 sft 78 per sft 78 15724.8
3 Carpenter Carpenter 3 nos 700 per day 700 2100
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter Helper 6 nos 550 per day 550 3300
5 Scafolding LS 400
6 Carrying to site in/c sundries LS 1000
Sub-Total 35284.8
Contractor's Profit 10% 0.1 3528.48
Contractor's Overhead Expenses 3.5% 0.035 1234.97
Total 40048.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3247.15
Grand Total 43295.4
Rate per sft 225.49
Rate per sqm 2427.17