Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | T-section (main T) for false ceiling(Anodized at any colour) Main T-section: 4 x 10'- 0"= 40.00 rft | 40 | rft | 28 | per foot | 28 | 1120 | |
| 2 | T-section (cross T) for false ceiling(Anodized at any colour) Coss T-section 4 x 10' - 0"=40rft considering 33% reduction in cross T length | 26.8 | rft | 24 | per foot | 24 | 643.2 | |
| 3 | L-section for wall and ceiling(Anodized at any colour) Angle or L-section: 4 x 10'- 0"= 40.00 rft | 40 | rft | 23 | per foot | 23 | 920 | |
| Sub-Total | 2683.2 | |||||||
| Contractor's Profit | 10% | 0.1 | 268.32 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 93.91 | |||||
| Total | 3045.43 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 246.93 | ||||
| Grand Total | 3292.36 | |||||||
| Rate per sft | 32.92 | |||||||
| Rate per sqm | 354.35 | |||||||