Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Sand cement solid block (SCSB) (250x115x115)mm SCSB (250x115x115) | 290 | nos | 12000 | per % 0 nos | 12 | 3480 | |
| 2 | Sand (F.M. 0.8) Fine sand | 4.9 | cft | 1670 | per % cft | 16.7 | 81.83 | |
| 3 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 4 | Skilled labour Skilled Labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 5 | Ordinary labour Local carriage, sundries, T & P etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| Sub-Total | 4119.33 | |||||||
| Contractor's Profit | 10% | 0.1 | 411.93 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 144.18 | |||||
| Total | 4675.44 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 379.09 | ||||
| Grand Total | 5054.53 | |||||||
| Rate per sft | 50.55 | |||||||
| Rate per per sqm | 544.12 | |||||||