Breakup

03.3.1 Brick on end edging with 1st class brick (BDS 208) including preparation of bed and filling the interstices with local sand, leveling, maintaining alignment and grid etc. all complete and accepted by the Engineer-in-charge

Considering 100 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 250 nos 10000 per % 0 nos 10 2500
2 Sand (F.M. 0.8) Fine sand 2 cft 1670 per % cft 16.7 33.4
3 Mason / Mosaic mistry Mason 0.2 no 700 per day 700 140
4 Skilled labour Skilled labour 0.5 no 600 per day 600 300
5 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 44 44
Sub-Total 3017.4
Contractor's Profit 10% 0.1 301.74
Contractor's Overhead Expenses 3.5% 0.035 105.61
Total 3424.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 277.68
Grand Total 3702.43
Rate per rft 37.02
Rate per per rm 121.46