Breakup

18.4.3 Supplying fitting and fixing of M.S. fixed louver made of 25mm x 25mm x 5mm M.S. Angle as outer frame, 2mm thick 25mm x 18mm MS sheet box section at 75mm c/c as internal horizontal member fixing with outer frame including scafolding, royal bolt, anchoring, welding, grinding, welder, helper and all accessories complete in all respect as per drawing and accepted by the Engineer-in-charge. (Rate is excluding cost of polish/ paint etc. of any type).

Considering area 1x5'-0''x2'-6''=12.50Sft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. angle, T and Z-section, Channel etc. (a)Cost of materials: i)25mmx25mmx5mm M.S angle Outer frame:((3x5'-0''= 15rft + 2x2'-6''=5rft)=20rft + Add 5% wastage=1rft)=21rft =6.40rm x1.766 kg/rm = 11.30kg 11.3 kg 70000 per M. ton 70 791
2 18/20/22 BWG MS Sheet/plate ii)25mmx18mm M.S sheet box section 2mm thick(3''c/c): 21x0'-4''x3'-0''= 21sft + Add 5% wastage= 1.05sft)=22.05sft=2.05sqm x 16kg/sqm = 32.80kg 32.8 kg 77000 per M. ton 77 2525.6
3 M.S. plain bar and F.I. bar (non-structural use) iii)Flat bar (20mm x 20mm x 3mm) (2x5'-0''= 10 rft + Add 5% wastage=0.50rft)=10.5rft =3.20rm x 0.471kg/rm = 1.51kg 1.51 kg 70000 per M. ton 70 105.7
4 Workshop charges (for making M.S sheet into box and fitting to the angle including cutting, welding, grinding,welder, helper, etc. all accessories) LS 3000
5 Carrying Charge for steel materials from market to work shop in/c loading and unloading LS 1000
6 Fittings & fixing at the site in/c making hole, concreting, anchoring, welding, scaffolding, etc. LS 700
Sub-Total 8122.3
Contractor's Profit 10% 0.1 812.23
Contractor's Overhead Expenses 3.5% 0.035 284.28
Total 9218.81
Add VAT with adjustment factor. 1.08108 7.5% 0.075 747.47
Grand Total 9966.28
Rate per sft 797.28
Rate per sqm 8581.92
Help