Considering 1 no of Skirting,size: 6'-0" x 0'-6" 3.00 sft For Myanmar(Burma) Teak wood with Garjan wood framing Wood Required (BT)=1x6'-0''x0'-6''x0'-0.5" = 0.125 cft (finished). Garjan =4x0-2''x0'-1.5''x0'-6" = 0.042 cft (finished).
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Myanmar(Burma) teak Cost of Myanmar(Burma) Teak wood | 0.125 | cft | 7100 | per cft | 7100 | 887.5 | |
| 2 | Garjan/Jam/local Sal Cost of Garjan wood | 0.042 | cft | 2200 | per cft | 2200 | 92.4 | |
| 3 | Myanmar(Burma) teak Accessories, royel plug,screw,nails, drill machine charges,Carrying etc. | 0.125 | cft | 7100 | per cft | 355 | 44.38 | |
| 4 | Carpenter Carpenter | 0.125 | no | 700 | per day | 700 | 87.5 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| Sub-Total | 1249.28 | |||||||
| Contractor's Profit | 10% | 0.1 | 124.93 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 43.72 | |||||
| Total | 1417.93 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 114.97 | ||||
| Grand Total | 1532.9 | |||||||
| Rate per sft | 511 | |||||||
| Rate per sqm | 5500.4 | |||||||