Breakup

03.3.2 Brick on end edging with Automatic machine made 1st class brick (240x114x70)mm including preparation of bed and filling the interstices with local sand, leveling, maintaining alignment and grid etc. all complete and accepted by the Engineer-in-charge

Considering 100 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Automatic machine made 1st class standard bricks Bricks 250 nos 11500 per % 0 nos 11.5 2875
2 Sand (F.M. 0.8) Fine sand 2 cft 1670 per % cft 16.7 33.4
3 Mason / Mosaic mistry Mason 0.2 no 700 per day 700 140
4 Skilled labour Skilled labour 0.5 no 600 per day 600 300
5 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 44 44
Sub-Total 3392.4
Contractor's Profit 10% 0.1 339.24
Contractor's Overhead Expenses 3.5% 0.035 118.73
Total 3850.37
Add VAT with adjustment factor. 1.08108 7.5% 0.075 312.19
Grand Total 4162.56
Rate per rft 41.63
Rate per per rm 136.59