Breakup

03.3.3 Brick on end edging with Sand Cement Solid block (SCSB) (250x115x115)mm including preparation of bed and filling the interstices with local sand, leveling, maintaining alignment and grid etc. all complete and accepted by the Engineer-in-charge

Considering 100 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand cement solid block (SCSB) (250x115x115)mm SCSB 250 nos 12000 per % 0 nos 12 3000
2 Sand (F.M. 0.8) Fine sand 2 cft 1670 per % cft 16.7 33.4
3 Mason / Mosaic mistry Mason 0.2 no 700 per day 700 140
4 Skilled labour Skilled labour 0.5 no 600 per day 600 300
5 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 44 44
Sub-Total 3517.4
Contractor's Profit 10% 0.1 351.74
Contractor's Overhead Expenses 3.5% 0.035 123.11
Total 3992.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 323.7
Grand Total 4315.95
Rate per rft 43.16
Rate per per rm rm 141.61
Help