Considering: 1 x 8'-0" x 4'-9"=38.00sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak Chattogram Teak:((Frame Vertical 2x2x4'-9''x0'-1.5''x0'-1.5''=0.3cft+Horizontal frame for shelf 2x3x8'-0''x0'-1.5''x0'-1.5''=0.75cft+3x6x1'-8''x0'-1.5''x0'-1.5''=0.47cft+Top & Bottom shutter 1x2x8'-0''x1'-8''x0'-1''=2.22cft+Side Shutter 1x2x4'-9''x1'-8''x0'-1''=1.32cft+Front & back frame for shutter anchoring 2x1x8'-0''x0'-1''x0'-1.5''=0.17cft+Front shutter 1x1x8'-0''x4'-9''x0'-1''=3.17cft)=8.4sft+Wastage 5%=0.42cft)=8.82cft | 8.82 | sft | 4400 | per cft | 4400 | 38808 | |
| 2 | 18mm thick Garjan ply board 18mm thick Garjan ply board Back Side 1 x 8'-0" x 4'-9" 38.00 sft Wastage 5% 1.90 sft =39.90 sft | 39.9 | sft | 110 | per sft | 110 | 4389 | |
| 3 | S.S. Chain Hinge S.S Chain Hinge | 6 | nos | 250 | each | 250 | 1500 | |
| 4 | 2" Magnet Magnet | 12 | nos | 45 | each | 45 | 540 | |
| 5 | SS Screws S.S Screws | 6.25 | dozen | 30 | per doz. | 30 | 187.5 | |
| 6 | Nails and wires Nail | 0.5 | kg | 70 | per kg | 70 | 35 | |
| 7 | Metal Handle Metal Handle (2 x6) | 12 | nos | 210 | each | 210 | 2520 | |
| 8 | Rubber gum Gum | 2 | kg | 655 | per kg | 655 | 1310 | |
| 9 | lock Lock | 6 | nos | 200 | each | 200 | 1200 | |
| 10 | Carpenter Carpenter | 1.5 | nos | 700 | per day | 700 | 1050 | |
| 11 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter Helper | 4.5 | nos | 550 | per day | 550 | 2475 | |
| 12 | Moulding for furniture work Moulding Bottom 2 x 1 x 8'-0'' x 0'-3'' 4.00 sft Top & middle 1 x 1 x 8'-0'' x 0'-1'' 0.67 sft Bottom 2 side 1 x 2 x 1'-8'' x 0'-3'' 0.83 sft Vertical side 1 x 2 x 4'-9'' x 0'-2.5'' 1.98 sft =7.48 sft | 7.48 | sft | 851 | per sft | 851 | 6365.48 | |
| 14 | 18mm thick BT ply board Cost of BT Ply board | 72.62 | sft | 145 | per sft | 145 | 10529.9 | |
| 13 | Carrying to site in/c sundries | LS | 700 | |||||
| Sub-Total | 71609.88 | |||||||
| Contractor's Profit | 10% | 0.1 | 7160.99 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2506.35 | |||||
| Total | 81277.22 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 6590.04 | ||||
| Grand Total | 87867.26 | |||||||
| Rate per sft | 2312.29 | |||||||
| Rate per sqm | 24889.49 | |||||||