considering: 1 x 2'-6" x 7'-0" =17.50sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak A) cost of materials : ⅰ)Chattogram Teak:(Frame Horizontal 2x1x7'-0''x0'-2.25''x0'-1.75''=0.38cft + Vertical 4x1x2'-6''x0'-2.25''x0'-1.75''=0.27cft + Edge bit Horizontal 2x3x2'-2''x0'-1''x0'-1''=0.09 cft + Vertical 3x4x2'-3''x0'-1''x0'-1''=0.19cft)=0.93cft + Wastage5%=0.05cft)=0.98cft | 0.98 | cft | 4400 | per cft | 4400 | 4312 | |
| 2 | 12 mm thick laminated vinyl board : 550 kg/m3 ii)12mm thick laminated vinayle board:(Shelf 1x1x7'-0"x1'-8" =11.67sft + Wastage5% =0.58sft)=12.25sft | 12.25 | sft | 68 | per sft | 68 | 833 | |
| 3 | S.S. Chain Hinge ⅰ) S.S Chain Hinge | 3 | nos | 250 | each | 250 | 750 | |
| 4 | 2" Magnet ⅰi) Magnet | 12 | nos | 45 | each | 45 | 540 | |
| 5 | SS Screws ⅰii) S.S Screws | 4.2 | dozen | 30 | per doz. | 30 | 126 | |
| 6 | Metal Handle ⅰv) Metal Handle | 6 | nos | 210 | each | 210 | 1260 | |
| 7 | Rubber gum v) Gum | 1 | kg | 655 | per kg | 655 | 655 | |
| 8 | Carpenter i) Carpenter | 2 | nos | 700 | per day | 700 | 1400 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator ii) Carpenter Helper | 3 | nos | 550 | per day | 550 | 1650 | |
| 11 | 18mm thick B.T. Marine ply board Cost of Marine board | 23.24 | sft | 190 | per sft | 190 | 4415.6 | |
| 10 | Carrying to site in/c sundries | LS | 700 | |||||
| Sub-Total | 16641.6 | |||||||
| Contractor's Profit | 10% | 0.1 | 1664.16 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 582.46 | |||||
| Total | 18888.22 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1531.48 | ||||
| Grand Total | 20419.7 | |||||||
| Rate per sft | 1166.86 | |||||||
| Rate per sqm | 12560.08 | |||||||