Considering a panel of 10'-0'' x 12'-0''= 120 sft. of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Garjan/Jam/local Sal 2)"Supplying, fitting and fixing of imported wood accoustic panel",Consider 1No Panel,Considering a panel of 10'-0'' x 12'-0''= 120 sft. of work a)Cost of materials:i)Garjan wood:batten 7x10'-0''x2''x1.5"=1.46cft + 6x12'-0''x2.0''x1.5"=1.50cft)=2.96cft + Add 5% wastage=0.15cft)=3.11cft | 3.11 | cft | 2200 | per cft | 2200 | 6842 | |
| 2 | Fire rated Wood Acoustic Panel (WAP) 2(b)Cost of Imported wood accoustic panel:1x10'-0''x12'-0"=120sft + Add 5% wastage=6 sft)=126sft | 126 | sft | 500 | per sft | 500 | 63000 | |
| 3 | Fire rated Wood Acoustic Panel (WAP) (Cost of Keel, side clip, middle clip)(5% cost of wood accoustic panel) | 126 | sft | 500 | per sft | 25 | 3150 | |
| 4 | Carpenter Cost of fitting,fixing,cutting to sizes,leveling,finishing,Scaffolding (B.T vennered) : Carpenter | 7 | nos | 700 | per day | 700 | 4900 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 7 | nos | 550 | per day | 550 | 3850 | |
| 6 | Scaffolding | LS | 300 | |||||
| 7 | Local carrige | LS | 700 | |||||
| Sub-Total | 82742 | |||||||
| Contractor's Profit | 10% | 0.1 | 8274.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2895.97 | |||||
| Total | 93912.17 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 7614.49 | ||||
| Grand Total | 101526.66 | |||||||
| Rate per sft | 846.06 | |||||||
| Rate per sqm | 9106.99 | |||||||