Considering a panel of 10'-0'' x 12'-0''= 120 sft. of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm thick commercial veneer 2)"Supplying, fitting and fixing of imported wood accoustic panel",Consider 1No Panel,Considering a panel of 10'-0''x12'-0''=120 sft. of work: a)Cost of materials i)12 mm commercial veneer :(1x10'-0''x12'-0"=120sft + Add 5% wastage=6sft)=126sft | 126 | sft | 73 | per sft | 73 | 9198 | |
| 2 | 5mm thick Garjan ply board (ii)5 mm garjon ply board : (1x10'-0''x12'-0"=120sft + Add 5% wastage=6 sft)=126sft | 126 | sft | 50 | per sft | 50 | 6300 | |
| 3 | 50 mm thick polyester/fibreglass insulation (iii)50 mm thick Polyester insulation / Fiberglass Insulation : 1x10'-0''x12'-0"=120sft + Add 5% wastage=6sft)= 126sft | 126 | sft | 30 | per sft | 30 | 3780 | |
| 4 | polyester fabrics (iv)Fabric : (1x10'-0''x12'-0"=120sft + Add 5% wastage=6 sft)=126sft | 126 | sft | 73 | per foot | 73 | 9198 | |
| 5 | Carpenter 2(c) Cost of fitting,fixing,cutting to sizes,leveling,finishing,Scaffolding : Carpenter | 4 | nos | 700 | per day | 700 | 2800 | |
| 6 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 8 | nos | 550 | per day | 550 | 4400 | |
| 7 | Scaffolding | LS | 300 | |||||
| 8 | Local carrige | LS | 700 | |||||
| Sub-Total | 36676 | |||||||
| Contractor's Profit | 10% | 0.1 | 3667.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1283.66 | |||||
| Total | 41627.26 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3375.18 | ||||
| Grand Total | 45002.44 | |||||||
| Rate per sft | 375.02 | |||||||
| Rate per sqm | 4036.72 | |||||||