Breakup

03.4.1 Lean / blinding concrete in foundation (1:3:6) with cement, brick chips and sand of F.M. 1.2

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 (1:3:6) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete 100 cft 14983 % cft 149.83 14983
2 Laying concrete (1000 cft per day using one mixture machine) Laying / placing concrete 100 cft 1999.5 % cft 20 2000
3 Ordinary labour Curing for 7 days 1 LS 550 per day 229.17 229.17
4 Timber for formwork Extra cost of wood for side shutter: for 100 cft 2 x 60'-0" x 4" x 1"= 3.33 cft 2 x 5'-0" x 4" x 1"= 0.28 cft 10 x 6" x 2" x 1" = 0.07 cft 3.68 cft Add 5% wastage 0.18 cft 3.86 cft (Using 6 times) 3.86 cft 550 per cft 91.67 353.85
5 Placing and removing of shutter for formwork Labour for side shutter 2 x 60'-0" x 4" = 40.00 sft 2 x 5' - 0" x 4" = 3.33 sft 43.33 sft 43.33 SFT 18 per sft 9 389.97
Sub-Total 17955.99
Contractor's Profit 10% 0.1 1795.6
Contractor's Overhead Expenses 3.5% 0.035 628.46
Total 20380.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1652.43
Grand Total 22032.48
Rate per cft 220.32
Rate per cum 7780.6
Help