18.7.3.2 Supplying, fitting and fixing of 15 mm thick Fire retardent, heat Insulated, Acoustic Mineral fiber board ceiling, (drop/ plain/ straight/ curve) (Made in UK/Germany/ Italy/ France or equivalent quality product) with high grade mineral wool, surface finish with white ultra vinyl latex paint, surface treatment-film coating, anti-fungal & anti bacterial humidity resistant greater than 90%, light reflectivity more than 90%, NRC value 0.60- 0.90, density-290-315 kg/m3, size of board: 600mm x 600mm, of imcombustible materials, framing by aluminium T-bar of natural anodized finish suspended in 600 mm x 600 mm grid from ceiling using butterfly hanger with adjustable clip/ locking clips etc. including cost of all materials, electricity, accessories, scaffoldings, labour for installation, screws, nails, rivet etc. all complete as per drawing, architectural and acoustic design (NRC 0.6-0.9) and accepted by the Engineer-in-charge. Measurement will be taken as per finished surface area. The brick/ RCC surface shall be dry and damp-proof. (This item is for acoustic work in auditorium, Hall Room, Seminar Room etc.) (Rate is excluding cost of polish/ paint etc. of any type).

Considering : 10'-0"X10'-0" = 100 sft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 15 mm thick acoustic Mineral fiber board (European standard) 15 mm thick acoustic Mineral fiber board 10'-0" X 10'-0' = 100.00 sft Add 5% wastage= 5.00 sft =105.00 sft 105 sft 220 per sft 220 23100
2 T-section (main T) for false ceiling(Anodized at any colour) Main T-section: 4 x 10'- 0"= 40rft 40 rft 28 per foot 28 1120
3 T-section (cross T) for false ceiling(Anodized at any colour) Coss T-section 4 x 10' - 0"= 40rft 40 rft 24 per foot 24 960
4 L-section for wall and ceiling(Anodized at any colour) Angle or L-section: 4 x 10'- 0"= 40rft 40 rft 23 per foot 23 920
5 Skilled technician Skilled Technician 1.5 nos 1200 per day 1200 1800
6 Skilled labour Skilled Labour 3 nos 600 per day 600 1800
7 Ordinary labour Ordinary Labour 3 nos 550 per day 550 1650
8 Scaffolding LS 400
9 Carrying to site in/c sundries LS 700
Sub-Total 32450
Contractor's Profit 10% 0.1 3245
Contractor's Overhead Expenses 3.5% 0.035 1135.75
Total 36830.75
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2986.27
Grand Total 39817.02
Rate per sft 398.17
Rate per sqm 4285.9