Considering 100 cft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (1:3:6) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete | 100 | cft | 14983 | % cft | 149.83 | 14983 | |
| 2 | Laying concrete (1000 cft per day using one mixture machine) Laying / placing concrete | 100 | cft | 1999.5 | % cft | 20 | 2000 | |
| 3 | Mason / Mosaic mistry Extra Mason for floor finish | 0.5 | no | 700 | per day | 700 | 350 | |
| 4 | Ordinary labour Curing for 7 days | 1 | LS | 550 | per day | 229.17 | 229.17 | |
| Sub-Total | 17562.17 | |||||||
| Contractor's Profit | 10% | 0.1 | 1756.22 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 614.68 | |||||
| Total | 19933.07 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1616.19 | ||||
| Grand Total | 21549.26 | |||||||
| Rate per cft | 215.49 | |||||||
| Rate per per cum | 7610.03 | |||||||