03.4.2 Lean / blinding concrete in floor (1:3:6) with cement, brick chips and sand of F.M. 1.2

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 (1:3:6) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete 100 cft 14983 % cft 149.83 14983
2 Laying concrete (1000 cft per day using one mixture machine) Laying / placing concrete 100 cft 1999.5 % cft 20 2000
3 Mason / Mosaic mistry Extra Mason for floor finish 0.5 no 700 per day 700 350
4 Ordinary labour Curing for 7 days 1 LS 550 per day 229.17 229.17
Sub-Total 17562.17
Contractor's Profit 10% 0.1 1756.22
Contractor's Overhead Expenses 3.5% 0.035 614.68
Total 19933.07
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1616.19
Grand Total 21549.26
Rate per cft 215.49
Rate per per cum 7610.03