Considering 1 No. rolling shutter Considering 10'-0" x 6'-0"= 60 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 0.45 mm thick C.I. sheet: 24 SWG G.P. sheet with 1/2" dia folding at the other end (@ 1 Ibs per rft) 44 (2.75"+3.14 x 0.5"+3.14 x 0.375) x 10'-0" = 121.00 sft Side patty: 2 x 10'-0" x 0'-3"= 5.00 sft 126.00 sft Add 5% wastage= 6.05 sft 132.05 sft = 132.05 lbs | 132.05 | lbs | 79000 | per M. ton | 35.83 | 4731.35 | |
| 2 | 18/20/22 BWG MS Sheet/plate 26 SWG cover sheet: @ 0.85 Ibs per sft 6'-0" x 4'-0"= 24.0 sft Add 5% wastage= 1.2 sft 25.2 sft = 21.42 Ibs | 21.42 | lbs | 77000 | per M. ton | 34.92 | 747.99 | |
| 3 | 38 mm/1.5" dia G.I. pipe 1.5" dia G.I. pipe | 6.33 | rft | 175 | per foot | 175 | 1107.75 | |
| 4 | M.S. angle, T and Z-section, Channel etc. 1" x 1" x 1/8" M.S. angle: @ 0.8 per rft: 1 x 6'-0"= 6 rft = 4.8 lbs | 4.8 | lbs | 70000 | per M. ton | 31.75 | 152.4 | |
| 5 | 18/20/22 BWG MS Sheet/plate 1/4" thick M.S. plate: @ 10.21 lbs per sft Side guide: 2 x 2 x 4" x 10'-6"= 14.0 sft Mid guide: 2 x 6" x 10'-6"= 10.5 sft 4 x 0'-2" x 0'-3"= 0.17 sft = 24.67 sft Add wastage 5%= 1.23 sft 25.90 sft = 264.44 Ibs | 264.44 | lbs | 77000 | per M. ton | 34.92 | 9234.24 | |
| 6 | M.S. plain bar and F.I. bar (non-structural use) 1" x 1/8" F.I. bar: @ 0.425 Ibs per rft Side guide channel: 2 x 2 x 10'-0"= 40 rft Mid guide channel: 2 x 10'-0"= 20 rft Guide channel to punkha: 2 x 2'-3"= 4.5 rft Guide channel to handle: 2 x 0'-9"= 1.5 rft = 66.0 rft Add 5% wastage= 3.3 rft 69.3 rft = 29.4525 Ibs | 29.4525 | lbs | 70000 | per M. ton | 31.75 | 935.12 | |
| 7 | 18/20/22 BWG MS Sheet/plate 1/8" thick M.S. plate for punkha & folded plate: @ 5.10 lbs per sft 2 x 1'-3" x 1'-0"= 2.50 sft 1 x 6'-0" x 0'-3"= 1.50 sft = 4.00 sft Add 5% wastage= 0.20 sft 4.20 sft = 12.75 Ibs | 12.75 | lbs | 77000 | per M. ton | 34.92 | 445.23 | |
| 8 | China made spring for rolling shutter Best quality china made spring: 3 x 11'-0"= 33 rft | 33 | rft | 55 | per foot | 55 | 1815 | |
| 9 | Spring box for rolling shutter Spring box | 3 | nos | 80 | each | 80 | 240 | |
| 10 | 12 mm dia nut-bolt Nut bolt, 1/2" dia maximum 2.5" long | 18 | nos | 12 | each | 12 | 216 | |
| 11 | Rivets (normal) Rivet: Side patty= 176 nos For fixing top tail= 9 nos For fixing lower plate= 40 nos = 225 nos | 225 | nos | 2 | each | 2 | 450 | |
| 12 | Rivets (normal) For guide channel= 20 nos | 20 | nos | 2 | each | 2 | 40 | |
| 13 | 150 mm long clamp 1" x 1/4" x 0'-9" clamps | 8 | nos | 37 | each | 37 | 296 | |
| 14 | Electrodes including electricity Electrodes | 30 | nos | 10 | each | 10 | 300 | |
| 15 | Grease/lubricant etc. Lubricant, greese: | 1 | lbs | 65 | per Ib | 65 | 65 | |
| 16 | Ordinary labour Cutting, folding both sides, rolling, locking individual strip, stitching or riveting side patty etc. | 44 | pcs | 550 | per day | 33 | 1452 | |
| 17 | Welder Welder/fabricator | 2 | nos | 700 | per day | 700 | 1400 | |
| 18 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 2 | nos | 550 | per day | 550 | 1100 | |
| 19 | Ordinary labour Carrying materials to work-shop and shutter to site | 1 | LS | 550 | per day | 550 | 550 | |
| 20 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Making holes | 8 | nos | 550 | per day | 22.92 | 183.36 | |
| 21 | Plain concrete (1:2:4) with brick chips Plain concrete: (1:2:4) 8 x 6" x 6" x 6"= 1.00 cft | 1 | cft | 20151.67 | % cft | 201.52 | 201.52 | |
| 22 | 1/2 " thick plaster (1:4) 1/2" plaster (1:4) to repair walls. 3 x 10'-0" x 1'-0"= 30 sft | 30 | sft | 23.22 | sft | 23.22 | 696.6 | |
| 23 | Mason / Mosaic mistry Mason | 0.5 | no | 700 | per day | 700 | 350 | |
| 24 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 25 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 26 | Welder Welder/ fabricator | 0.5 | no | 700 | per day | 700 | 350 | |
| 27 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 28 | Workshop Charge 19.6 Workshop charge | 1 | - | 25277.82 | Unit | 1263.89 | 1263.89 | |
| Sub-Total | 29148.45 | |||||||
| Contractor's Profit | 10% | 0.1 | 2914.85 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1020.2 | |||||
| Total | 33083.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2682.44 | ||||
| Grand Total | 35765.94 | |||||||
| Rate per sft | 596.1 | |||||||
| Rate per sqm | 6416.42 | |||||||