Breakup

19.8.2 for S.S. Grade A201

Considering 1 No. of gate Considering 12'-0" x 6'-0"= 72 sft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 37 mm dia stainless steel (1.5 mm thick) pipe-(grade A201) 37 mm x 1.5 mm ss round pipe section as vertical section (6+3+6) x 9= 135.0 rft Add wastage 5%= 6.75 rft = 141.75 rft 141.75 rft 138 per foot 138 19561.5
2 25 mm x 25 mm, 1.5mm thick SS square box (grade A201 ) 25 mm x 25 mm x 1.5 mm ss box section 4.25x8x3= 102 rft Add wastage 5%= 5.1 rft = 107.10 rft 107.1 rft 115 per foot 115 12316.5
3 38 mm x 12 mm, 1.5 mm thick SS box (grade A201) 12mm x 38mm x 1.5 mm ss box section 4x1x8= 32.00 rft Add wastage 5%= 1.60 rft = 33.60 rft 33.6 rft 126 per foot 126 4233.6
4 SS hollow round pipe 1.5mm thickness 12mm SS hollow round pipe 1.5mm thickness 17x1'-9"= 29.75 rft 9.07 rm 0.444 kg/rm = 4.02708 kg/rm 4.02708 kg/rm 300 per kg 300 1208.12
5 SS hollow round pipe 1.5mm thickness 25mm SS hollow round pipe 1.5mm thickness 2x12+9x2= 42.00 rft 12.80 rm 0.924 kg/rm = 11.8272 kg/rm 11.8272 kg/rm 300 per kg 300 3548.16
6 1'-6'' Long 25 mm SS Handle SS Handle 1 set 450 each 450 450
7 75mm dia SS Wheel SS Wheel 10 nos 1800 each 1800 18000
8 75 mm - 150 mm M.S. clamp SS Locking clamp 8 nos 32 each 64 512
9 4mm thick SS base plate SS 4mm base plate 4 kg 250 per kg 250 1000
10 Solid SS royal bolt with cap SS royal bolt with cap 72 nos 40 each 40 2880
11 Electrodes including electricity Electrodes 250 pc 10 each 10 2500
12 SS hole cutting Hole cutting 63 nos 10 each 10 630
13 Welder Welder / fabricator 5 nos 700 per day 700 3500
14 Ordinary labour Helper/Ordinary labour 5 nos 550 per day 550 2750
17 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Making holes 6 nos 550 per day 22.92 137.52
18 Plain concrete (1:2:4) with brick chips Plain concrete: (1:2:4) 6 x 10" x 6" x 6"= 1.25 cft 16'-0" x 6" x 4"= 2.67 cft 2 x 4 x 6" x 4"= 1.33 cft = 5.25 cft 5.25 cft 20151.67 % cft 201.52 1057.98
19 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
20 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 1 no 550 per day 550 550
21 Ordinary labour Ordinary labour 1 no 550 per day 550 550
22 Workshop Charge 19.8.2 Workshop charge 1 - 85094.73 Unit 4254.74 4254.74
15 Polishing charge LS 500
16 Carrying materials to work-shop & gate to site LS 550
Sub-Total 81390.12
Contractor's Profit 10% 0.1 8139.01
Contractor's Overhead Expenses 3.5% 0.035 2848.65
Total 92377.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7490.08
Grand Total 99867.86
Rate per sft 1387.06
Rate per sqm 14930.31
Help