Considering 100 cft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | (1:2:4) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete | 100 | cft | 17573 | % cft | 175.73 | 17573 | |
| 2 | Laying concrete (1000 cft per day using one mixture machine) Laying / placing concrete | 100 | cft | 1999.5 | % cft | 20 | 2000 | |
| 3 | Ordinary labour Curing for 7 days | 1 | LS | 550 | per day | 229.17 | 229.17 | |
| 4 | Timber for formwork Extra cost of wood for side shutter: for 100 cft 2 x 60'-0" x 4" x 1"= 3.33 cft 2 x 5'-0" x 4" x 1"= 0.28 cft 10 x 6" x 2" x 1" = 0.07 cft 3.68 cft Add 5% wastage 0.18 cft = 3.86 cft (Using 6 times) | 3.86 | cft | 550 | per cft | 91.67 | 353.85 | |
| 5 | Placing and removing of shutter for formwork Labour for side shutter 2 x 60'-0" x 4" = 40.00 sft 2 x 5' - 0" x 4" = 3.33 sft = 43.33 sft | 43.33 | sft | 18 | per sft | 9 | 389.97 | |
| Sub-Total | 20545.99 | |||||||
| Contractor's Profit | 10% | 0.1 | 2054.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 719.11 | |||||
| Total | 23319.7 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1890.78 | ||||
| Grand Total | 25210.48 | |||||||
| Rate per cft | 252.1 | |||||||
| Rate per cum | 8902.91 | |||||||