Breakup

03.5.2 Mass concrete in floor (1:2:4) with brick chips and local sand of F.M. 1.2.

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 (1:2:4) with BRICK CHIPS and sand of F.M. 1.2 Cost of concrete 100 cft 17573 % cft 175.73 17573
2 Laying concrete (1000 cft per day using one mixture machine) Laying / placing concrete 100 cft 1999.5 % cft 20 2000
3 Mason / Mosaic mistry Extra Mason for floor finish 0.5 no 700 per day 700 350
4 Ordinary labour Curing for 7 days 1 LS 550 per day 229.17 229.17
Sub-Total 20152.17
Contractor's Profit 10% 0.1 2015.22
Contractor's Overhead Expenses 3.5% 0.035 705.33
Total 22872.72
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1854.54
Grand Total 24727.26
Rate per cft 247.27
Rate per cum 8732.34
Help