Breakup

20.3.1 With the provision of hand rail of size: 150 mm x 62 mm (finished)

Considering 1 No. of railing Clear G.I. pipe height 34" + embedded into RCC 6" Lenght of G.I. pipe = 3'-4" Railing Area = 9'-9" x 2'-10"= 27.6 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 13 mm/1/2" dia G.I. pipe 1/2" dia G.I. pipe of 2.65 mm thick: 10 x 3'-4"= 33.33 rft Add wastage 5%= 1.67 rft = 35.00 rft 35 rft 61 per foot 61 2135
2 18/20/22 BWG MS Sheet/plate 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft 10 x 2" x 2"= 0.28 sft Add wastage 5%= 0.01 sft = 0.29 sft = 2.96 Ibs 2.96 lbs 77000 per M. ton 34.92 103.36
3 M.S. plain bar and F.I. bar (non-structural use) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs per rft 1 x 9'-9"= 9.75 rft Add wastage 5%= 0.49 rft = 10.24 rft = 13.11 lbs 13.11 lbs 70000 per M. ton 31.75 416.24
4 Electrodes including electricity Electrodes: 80 nos 10 each 10 800
5 Welder Welder / fabricator 0.5 nos 700 per day 700 350
6 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 1 no 550 per day 550 550
7 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting: 2" x 2" x 6" size grooves 10 nos 550 per day 18.33 183.3
10 Plain concrete (1:2:4) with brick chips CC (1:2:4): 10 x 2" x 2" x 6"= 0.14 cft 0.14 cft 20151.67 % cft 201.52 28.21
11 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
12 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.5 no 550 per day 550 275
13 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
14 Welder Welder/fabricator 0.25 no 700 per day 700 175
15 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 0.5 no 550 per day 550 275
16 Workshop Charges 20.3.1 Work-shop charges: 1 - 5904.56 Unit 295.23 295.23
8 Carrying of materials to work-shop and fabricated materials to site: LS 450
Sub-Total 7586.34
Contractor's Profit 10% 0.1 758.63
Contractor's Overhead Expenses 3.5% 0.035 265.52
Total 8610.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 698.15
Grand Total 9308.64
Rate per sft 337.28
Rate per sqm 3630.48
Help