Considering 1 No. of railing Clear G.I. pipe height 34.5" + embedded into RCC 6" + 1.5" dia hand rail Lenght of G.I. pipe = 3'-4.5" Considering 10'-0" x 3'-0"= 30 sft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 13 mm/1/2" dia G.I. pipe 1/2" dia G.I. pipe of 2.65 mm thick 20 x 3'-4.5"= 67.50 rft Add wastage 5%= 3.38 rft = 70.88 rft | 70.88 | rft | 61 | per foot | 61 | 4323.68 | |
| 2 | 38 mm/1.5" dia G.I. pipe 1.5" dia G.I. pipe of 3.20 mm thick: 1 x 10'-0"= 10.00 rft Add wastage 5%= 0.50 rft = 10.50 rft | 10.5 | rft | 175 | per foot | 175 | 1837.5 | |
| 3 | 18/20/22 BWG MS Sheet/plate 2" x 2" x 1/4" M.S.plate: @ 10.2 Ibs per rft 20 x 2" x 2"= 0.56 sft Add wastage 5%= 0.03 sft = 0.59 sft = 6.02 lbs | 6.02 | lbs | 77000 | per M. ton | 34.92 | 210.22 | |
| 4 | Electrodes including electricity Electrodes in/c electricity | 80 | nos | 10 | each | 10 | 800 | |
| 5 | Welder Welder / fabricator | 0.5 | nos | 700 | per day | 700 | 350 | |
| 6 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 1 | no | 550 | per day | 550 | 550 | |
| 7 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 2" x 2" x 6" size grooves | 20 | nos | 550 | per day | 18.33 | 366.6 | |
| 10 | Plain concrete (1:2:4) with brick chips CC (1:2:4): 20 x 2" x 2" x 6" = 0.28 cft | 0.28 | cft | 20151.67 | % cft | 201.52 | 56.43 | |
| 11 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 12 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 13 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 14 | Welder Welder/fabricator | 0.25 | no | 700 | per day | 700 | 175 | |
| 15 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 16 | Workshop Charges 20.4.1 Work-shop charges: | 1 | - | 9071.4 | Unit | 453.57 | 453.57 | |
| 8 | Carrying of materials to work-shop and fabricated materials to site: | LS | 450 | |||||
| Sub-Total | 10848 | |||||||
| Contractor's Profit | 10% | 0.1 | 1084.8 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 379.68 | |||||
| Total | 12312.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 998.31 | ||||
| Grand Total | 13310.79 | |||||||
| Rate per sft | 443.7 | |||||||
| Rate per sqm | 4775.99 | |||||||