20.6.2.1 With MS box of size: 38 mm x 12 mm of 1.5 mm wall thikness

Considering 1 No. of railing Considering 9'-9" x 3'-6"= 34.125 sft.

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 18/20/22 BWG MS Sheet/plate 75mm x50mm x 3mm thick M.S. Box: @ 4.25 lbs per rft. 4 x 3'-3"= 13.00 rft. Add wastage 5%= 0.65 rft. = 13.65 rft. = 58.01 Ibs. 58.01 lbs 77000 per M. ton 34.92 2025.71
2 18/20/22 BWG MS Sheet/plate 38mm x 12mm x 1.5mm M.S. Box: @ 0.80 Ibs. per rft. 9 x 9'-1"= 81.72 rft. Add wastage 5%= 4.09 rft. = 85.81 rft. = 68.65 lbs. 68.65 lbs 77000 per M. ton 34.92 2397.26
3 18/20/22 BWG MS Sheet/plate 4" x 4" x 1/4" thick M.S. plate: @ 2.55 lbs per sft. 4 x 4" x 4"= 0.45 sft. Add wastage 5%= 0.02 sft. = 0.47 sft. = 1.20 Ibs. 1.2 lbs 77000 per M. ton 34.92 41.9
4 M.S. plain bar and F.I. bar (non-structural use) 50mm x 6mm M.S. F.I. bar: @ 1.70 Ibs. per rft. 1 x 9'-9"= 9.75 rft. Add wastage 5%= 0.49 rft. = 10.24 rft. = 17.41 lbs. 17.41 lbs 70000 per M. ton 31.75 552.77
5 Electrodes including electricity Electrodes 160 nos 10 each 10 1600
6 Royal bolt 2" Royal Bolt 16 nos 57 each 57 912
7 Iron screws Iron Screws 3 dzn 18 per dzn 18 54
8 Welder Welder / fabricator 0.5 nos 700 per day 700 350
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 1.5 nos 550 per day 550 825
10 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
12 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 2" x 2" x 6" size grooves 10 nos 550 per day 18.33 183.3
13 Plain concrete (1:2:4) with brick chips CC (1:2:4): 20 x 2" x 2" x 6"= 0.14 cft 0.14 cft 20151.67 % cft 201.52 28.21
14 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
15 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.5 no 550 per day 550 275
16 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
17 Welder Welder/fabricator 0.25 no 700 per day 700 175
18 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 0.5 no 550 per day 550 275
19 Workshop Charges 20.6.2.1 Work-shop charges: 1 - 10308.65 Unit 515.43 515.43
11 Carrying of materials to work-shop and fabricated materials to site: LS 450
Sub-Total 12210.58
Contractor's Profit 10% 0.1 1221.06
Contractor's Overhead Expenses 3.5% 0.035 427.37
Total 13859.01
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1123.7
Grand Total 14982.71
Rate per sft 439.06
Rate per sqm 4726.04