Considering 1 No. of railing Considering 9'-9" x 3'-3"= 31.69 sft.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50mm x 6mm SS double plate newel post with SS knob 50mm x 6mm SS double plate newel post with SS Nob 1x4= 4.00 Nos | 4 | nos | 2500 | per rft | 2500 | 10000 | |
| 2 | 62 mm dia stainless steel (2 mm thick) pipe 62mm dia 2mm thick SS SS Hand rail 1 x 9'-9"= 9.75 rft. Add wastage 5%= 0.49 rft. = 10.24 rft. | 10.24 | rft | 285 | per foot | 285 | 2918.4 | |
| 3 | 20 mm dia stainless steel (2 mm thick) pipe 20mm dia SS pipe. 5 x 9'-9"= 48.75 rft. Add wastage 5%= 2.44 rft. = 51.19 rft. | 51.19 | rft | 76 | per foot | 76 | 3890.44 | |
| 4 | 6" x 4" x 1/4" thick S.S. plate 6" x 4" x 1/4" thick S.S. plate 4 x 1= 4.00 Nos. | 4 | nos | 225 | each | 225 | 900 | |
| 5 | Electrodes including electricity Electrodes with electricity: | 135 | nos | 10 | each | 10 | 1350 | |
| 6 | Royal bolt 50mm Royal Bolt | 12 | nos | 57 | each | 57 | 684 | |
| 7 | SS 12mm dia Royal Bolt cap SS 12mm dia Royal Bolt cap | 12 | dzn | 30 | each | 30 | 360 | |
| 8 | SS 62mm dia end cap SS 62mm dia end cap | 1 | no | 70 | each | 70 | 70 | |
| 9 | SS 20mm dia end cap SS 20mm dia end cap | 5 | nos | 40 | each | 40 | 200 | |
| 10 | Welder Welder / fabricator | 1 | no | 700 | per day | 700 | 700 | |
| 11 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 1.5 | no | 550 | per day | 550 | 825 | |
| 12 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 15 | Welder Welder/fabricator | 0.25 | nos | 700 | per day | 700 | 175 | |
| 16 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 17 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 13 | Work shop charge including Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc | LS | 1500 | |||||
| 14 | Carrying of materials to work-shop and fabricated materials to site: | LS | 450 | |||||
| Sub-Total | 25947.84 | |||||||
| Contractor's Profit | 10% | 0.1 | 2594.78 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 908.17 | |||||
| Total | 29450.79 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2387.9 | ||||
| Grand Total | 31838.69 | |||||||
| Rate per sft | 1004.7 | |||||||
| Rate per sqm | 10814.59 | |||||||