Breakup

20.11 Supplying, fitting and fixing stainless steel railing of standard height (approximately 225 mm above RCC or Brick wall) with 2 mm thick 62 mm dia SS pipe for hand-rail, 2 mm thick 40 mm dia vertical SS pipes @ 1200 mm c/c fitting and fixing with 65 mm x 55 mm x 6 mm SS base plate and fitting base plate with the surface by 50mm long royal bolt including welding, bending, fabricating, polishing all complete as per drawing, desing and specification etc all complete in all respect and accepted by Engineer-in-charge.

Considering 01 rail of Height approximately 225 mm above RCC or Brick wall = 1X 12'-0" = 12.00 rft rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 62 mm dia stainless steel (2 mm thick) pipe a) 62 mm dia SS pipe 1 X 12'-0" = 12.00 rft Add 5% wastage= 0.60 " =12.60 rft 12.6 rft 285 per foot 285 3591
2 40 mm dia stainless steel (2 mm thick) pipe-(grade A201) b) 40 mm dia SS pipe Vertical 4 X 0'-8" = 2.68 rft Add 5% wastage= 0.13 " = 2.81 rft 2.81 rft 170 per foot 170 477.7
3 65mm x 55mm, 6 mm thick SS Plate c) Base plate (65x55x6 mm) 4 nos 173 each 173 692
4 Royal bolt d) Royal bolt 8 nos 57 each 57 456
5 Welder i) Welder / Fabricator 0.1 nos 700 per day 700 70
6 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator ii) Welder helper 0.25 nos 550 per day 550 137.5
7 Electrodes including electricity Welding Rod(Electrode) 25 nos 10 each 10 250
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 2" x 2" x 6" size grooves 4 nos 550 per day 22.92 91.68
10 Plain concrete (1:2:4) with brick chips CC (1:2:4): 4 x 2" x 2" x 6" = 0.06 cft 0.06 cft 20151.67 % cft 201.52 12.09
11 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
12 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
8 Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc LS 50
13 Carring of Materials from market to work shop and workshop to site LS 100
Sub-Total 6377.97
Contractor's Profit 10% 0.1 637.8
Contractor's Overhead Expenses 3.5% 0.035 223.23
Total 7239
Add VAT with adjustment factor. 1.08108 7.5% 0.075 586.95
Grand Total 7825.95
Rate per rft 652.17
Rate per rm 2139.77
Help