Breakup

20.12.3 Supplying, fitting and fixing 50 mm dia finished Wooden railing on inner side of stair (50mm space from wall), fitting both sides by 2 mm thick 50 mm dia SS pipe caping one end of 250 mm length, fitting and fixing by a SS holder @ 1200 mm c/c welding with 65 mm x 55 mm x 6 mm SS base plate and fitting base plate on RCC or Brick wall by Royel Bolt including welding, bending, fabricating, all complete as per drawing, desing and specification etc all complete in all respect and accepted by Engineer-in-charge

Considering 01 no rail = 1X 12'-0" = 12.00 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Myanmar(Burma) teak i) Wood required 1 x 2.25" x 2.25" x 12'-0"= 0.42 cft Add wastage 5%= 0.02 cft = 0.44 cft 0.44 cft 7100 per cft 7100 3124
2 50 mm dia stainless steel (2 mm thick) pipe ii) 50 mm dia SS pipe 2 X 0'-10" = 1.83 rft Add 5% wastage= 0.09 " =1.92 rft 1.92 rft 225 per foot 225 432
3 Bottom cap for 40 mm dia SS pipe SS cap 2 nos 73 each 73 146
4 SS Glass Holder SS holder 4 nos 225 each 225 900
5 65 mm x 55 mm x 6 mm SS plate Base plate (65x55x6 mm) 4 nos 173 each 173 692
6 Royal bolt Royal bolt 8 nos 57 each 57 456
8 Carpenter Carpenter 0.15 no 700 per day 700 105
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 0.25 no 550 per day 550 137.5
10 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
11 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
7 Workshop charge including fabrication, welding, bending, making box, welding rod (Electrode), electricity, argon gas, filler rod, tungsten rod, gardening disk electricity, woven mop 240 GRT e LS 150
12 Polishing work LS 50
13 Carring of Materials from market to work shop and workshop to site LS 100
Sub-Total 6742.5
Contractor's Profit 10% 0.1 674.25
Contractor's Overhead Expenses 3.5% 0.035 235.99
Total 7652.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 620.49
Grand Total 8273.23
Rate per rft 689.42
Rate per rm 2261.99