Considering 01 no rail = 1X 12'-0" = 12.00 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Myanmar(Burma) teak i) Wood required 1 x 2.25" x 2.25" x 12'-0"= 0.42 cft Add wastage 5%= 0.02 cft = 0.44 cft | 0.44 | cft | 7100 | per cft | 7100 | 3124 | |
| 2 | 50 mm dia stainless steel (2 mm thick) pipe ii) 50 mm dia SS pipe 2 X 0'-10" = 1.83 rft Add 5% wastage= 0.09 " =1.92 rft | 1.92 | rft | 225 | per foot | 225 | 432 | |
| 3 | Bottom cap for 40 mm dia SS pipe SS cap | 2 | nos | 73 | each | 73 | 146 | |
| 4 | SS Glass Holder SS holder | 4 | nos | 225 | each | 225 | 900 | |
| 5 | 65 mm x 55 mm x 6 mm SS plate Base plate (65x55x6 mm) | 4 | nos | 173 | each | 173 | 692 | |
| 6 | Royal bolt Royal bolt | 8 | nos | 57 | each | 57 | 456 | |
| 8 | Carpenter Carpenter | 0.15 | no | 700 | per day | 700 | 105 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 10 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 11 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 7 | Workshop charge including fabrication, welding, bending, making box, welding rod (Electrode), electricity, argon gas, filler rod, tungsten rod, gardening disk electricity, woven mop 240 GRT e | LS | 150 | |||||
| 12 | Polishing work | LS | 50 | |||||
| 13 | Carring of Materials from market to work shop and workshop to site | LS | 100 | |||||
| Sub-Total | 6742.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 674.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 235.99 | |||||
| Total | 7652.74 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 620.49 | ||||
| Grand Total | 8273.23 | |||||||
| Rate per rft | 689.42 | |||||||
| Rate per rm | 2261.99 | |||||||