Considering 1 No. of verandha railing Considering 13'-0" x 3'-6"= 45.50 sft.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 62 mm dia stainless steel (2 mm thick) pipe 62mm dia, 2mm thick SS hand Rail 1 x 6'-0"= 6.00 rft. 2 x 3'-9"= 7.50 rft. 13.50 rft. Add wastage 5%= 0.68 rft. = 14.18 rft. | 14.18 | rft | 285 | per foot | 285 | 4041.3 | |
| 2 | 50 mm dia stainless steel (2 mm thick) pipe 50mm dia, 2mm thick SS vertical Post 5 x 3'-6"= 17.50 rft. Add wastage 5%= 0.88 rft. = 18.38 rft. | 18.38 | rft | 225 | per foot | 225 | 4135.5 | |
| 3 | 25 mm x 25 mm, 1.5mm thick SS square box (grade A304) 25mm x 25mm, 1.5mm thick SS square box 2 x 5 x 3'- 3"= 32.50 rft' 1x 11x 3'- 3"= 35.75 rft' 68.25 rft Add wastage 5%= 3.41 rft = 71.66 rft | 71.66 | rft | 150 | per foot | 150 | 10749 | |
| 4 | 38 mm x 38 mm, 1.5 mm thick SS box (grade A304) 38mm x 38mm, 1.5 mm thick SS 2 x 13'-0"= 26.00 rft. 26.00 rft. Add wastage 5%= 1.30 rft. = 27.30 rft. | 27.3 | rft | 220 | per foot | 220 | 6006 | |
| 5 | 65 mm x 55 mm x 6 mm SS plate 65mm x 55mm, 6 mm thick SS Plate 1 x 5= 5.00 Nos. | 5 | nos | 173 | each | 173 | 865 | |
| 6 | Electrodes including electricity Electrodes with electricity: | 150 | nos | 10 | each | 10 | 1500 | |
| 7 | Royal bolt 3" Royal Bolt | 6 | nos | 57 | each | 57 | 342 | |
| 8 | 62 mm dia end socket 62 mm dia End Socket | 2 | nos | 36 | each | 36 | 72 | |
| 9 | 62 mm dia SS bend 62 mm dia SS bend | 2 | nos | 73 | each | 73 | 146 | |
| 10 | 25 mm dia socket 25 mm Square end cap | 42 | nos | 15 | each | 15 | 630 | |
| 11 | Welder Welder / fabricator | 1 | nos | 700 | per day | 700 | 700 | |
| 12 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 2 | nos | 550 | per day | 550 | 1100 | |
| 13 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 16 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 17 | Welder Welder/fabricator | 0.25 | no | 700 | per day | 700 | 175 | |
| 18 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 14 | Carrying of materials to work-shop and fabricated materials to site: | LS | 350 | |||||
| 15 | Wokshop Charge incuding Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc | LS | 1500 | |||||
| Sub-Total | 33961.8 | |||||||
| Contractor's Profit | 10% | 0.1 | 3396.18 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1188.66 | |||||
| Total | 38546.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3125.4 | ||||
| Grand Total | 41672.04 | |||||||
| Rate per sft | 915.87 | |||||||
| Rate per sqm | 9858.42 | |||||||