Considering 1 No. of verandha railing Considering 13'-0" x 3'-6"= 45.50 sft.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 62 mm dia stainless steel (2 mm thick) pipe 62mm dia, 2mm thick SS hand Rail 1 x 6'-0"= 6.00 rft. 2 x 3'-6"= 7.00 rft. 13.00 rft. Add wastage 5%= 0.65 rft. = 13.65 rft. | 13.65 | rft | 285 | per foot | 285 | 3890.25 | |
| 2 | 75mm x 75 mm, 2mm thick SS vertical Post 75mm x 75 mm, 2 mm thick SS vertical Post 1x 5= 5.00 Nos | 5 | nos | 2000 | each | 2000 | 10000 | |
| 3 | 25 mm dia stainless steel (1.2 mm thick) pipe 25mm dia, 1.5 mm thick SS Pipe 8 x 6'-0"= 48.00 rft. 16 x 3'-6"= 56.00 rft. 104.00 rft. Add wastage 5%= 5.20 rft. = 109.20 rft. | 109.2 | rft | 100 | per foot | 100 | 10920 | |
| 4 | 25 mm dia SS knob 25mm dia SS Knob 5x 8= 40.00 Nos | 40 | nos | 100 | each | 100 | 4000 | |
| 5 | 6" x 6" x 1/4" thick S.S. plate 6" x 6" x 1/4" thick S.S. plate 5 x 1= 5.00 Nos. | 5 | nos | 250 | each | 250 | 1250 | |
| 6 | Electrodes including electricity Electrodes with electricity: | 120 | nos | 10 | each | 10 | 1200 | |
| 7 | Royal bolt 3" Royal Bolt | 20 | nos | 57 | each | 57 | 1140 | |
| 8 | 62 mm dia end socket 62 mm dia End Socket | 2 | nos | 36 | each | 36 | 72 | |
| 9 | 62 mm dia SS bend 62 mm dia SS bend | 2 | nos | 73 | each | 73 | 146 | |
| 10 | 25 mm dia socket 25 mm dia end cap | 16 | nos | 15 | each | 15 | 240 | |
| 11 | Welder Welder / fabricator | 1 | nos | 700 | per day | 700 | 700 | |
| 12 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 1.5 | nos | 550 | per day | 550 | 825 | |
| 13 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 16 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 17 | Welder Welder/fabricator | 0.25 | no | 700 | per day | 700 | 175 | |
| 18 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 14 | Carrying of materials to work-shop and fabricated materials to site: | LS | 350 | |||||
| 15 | Wokshop Charge incuding Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc | LS | 1500 | |||||
| Sub-Total | 38058.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 3805.83 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1332.04 | |||||
| Total | 43196.12 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3502.38 | ||||
| Grand Total | 46698.5 | |||||||
| Rate per sft | 1026.35 | |||||||
| Rate per sqm | 11047.63 | |||||||