Breakup

20.15.1 Supplying, fitting and fixing 10 mm thick tempered glass railing in verandah with 62mm dia 2 mm thick SS pipe for hand rail, 62 mm x 50 mm x 2 mm SS vertical box fitted with concrete slab by 100 mm x 55 mm x 6 mm SS plate @ 600 mm c/c and base plate fitting with the floor by 50mm long royal bolt including all fittings, fixtures as per drawing, desing and specification etc all complete in all respect and accepted by Engineer-in-charge.

Considering: 20'-0"x3'-6" =70.00 sft Cost related to SS work Part

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 62 mm dia stainless steel (2 mm thick) pipe a) 62 mm dia SS pipe fo hand rail 1 x 20'-0" = 20.00 rft Add 5% wastage = 1.00 rft = 21.00 rft 21 rft 285 per foot 285 5985
2 50 x 62 x 2 mm SS pipe post with glass holder b) 50 x 62 x 2mm SS box post with glass holder 36.21 rft 345 each 345 12492.45
3 65mm x 55mm, 6 mm thick SS Plate c) Base plate (100 x 55 x 6 mm) 11 nos 173 each 173 1903
4 Royal bolt d) Royal bolt 44 nos 57 each 57 2508
5 SS base cup 38 mm e) SS base cup 11 nos 230 each 230 2530
6 Welder i) Welder / Fabricator 1 nos 700 per day 700 700
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator ii) Welder helper 1.5 nos 550 per day 550 825
8 Ordinary labour Ordinay labour 2 nos 550 per day 550 1100
9 Scaffolding Scaffolding 50 sft 10 per sft 10 500
10 Electrodes including electricity Welding Rod(Electrode) 100 nos 10 each 10 1000
12 Tempered glass thickness 10.0mm Cost of 10mm thick Tempered glass in/c. 5% wastage 73.5 sft 280 sft 280 20580
13 Glass hole Glass hole 40 pcs 31 each 31 1240
14 25 mm dia SS knob SS knob 40 pcs 100 each 100 4000
15 Skilled technician Skilled Technician 0.5 no 1200 per day 1200 600
16 Semi skilled technician Semi skilled Technician 1 no 800 per day 800 800
17 Ordinary labour Ordinary labor for glass 2 nos 550 per day 550 1100
18 Welder Welder/fabricator 0.25 no 700 per day 700 175
19 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 0.5 no 550 per day 550 275
20 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
11 Work shop charge including Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc LS 1500
21 Carring of Materials from market to work shop and workshop to site LS 700
Sub-Total 60788.45
Contractor's Profit 10% 0.1 6078.85
Contractor's Overhead Expenses 3.5% 0.035 2127.6
Total 68994.9
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5594.18
Grand Total 74589.08
Rate per sft 1065.56
Rate per sqm 11469.69
Help