Considering 1 No. of verandha railing Considering 13'-0" x 3'-6"= 45.50 sft. exposed surface
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 18/20/22 BWG MS Sheet/plate 75mm x 38 mm, 3mm thick MS box Post M.S. hollow box 3" x 1.5" x 1/8" @ 3.828 lbs. per rft. 8 x 3'-6"= 28.00 rft. Add wastage 5%= 1.40 rft. = 29.40 rft. = 112.54 Ibs. | 112.54 | lbs | 77000 | per M. ton | 34.92 | 3929.9 | |
| 2 | 18/20/22 BWG MS Sheet/plate 50mm x 50mm, 3mm thick MS box @ 3.40 lbs. per rft. 1 x 6'-0"= 6.00 rft. 2 x 3'-6"= 7.00 rft. 13.00 rft. Add wastage 5%= 0.65 rft. = 13.65 rft. = 46.41 lbs | 46.41 | lbs | 77000 | per M. ton | 34.92 | 1620.64 | |
| 3 | Tempered glass thickness 10.0mm 10mm tempered glass 2x3'-0" x 3'-6"= 21.00 sft 2x3'-6" x 3'-6"= 24.50 sft 45.50 sft Add wastage 5%= 2.28 sft = 47.78 sft | 47.78 | sft | 280 | sft | 280 | 13378.4 | |
| 4 | MS Glass Holder MS Glass Holder =16.00 Nos | 16 | nos | 125 | each | 125 | 2000 | |
| 5 | 18/20/22 BWG MS Sheet/plate 6" x 4" x 1/4" thick MS. plate 8 x 6" x 4"= 1.33 sft. Add wastage 5%= 0.07 sft. = 1.40 sft. = 3.57 Ibs. | 3.57 | lbs | 77000 | per M. ton | 34.92 | 124.66 | |
| 6 | Royal bolt 2" Royal Bolt | 32 | nos | 57 | each | 57 | 1824 | |
| 7 | SS 12mm dia Royal Bolt cap 12mm dia Royal Bolt cap | 28 | nos | 30 | each | 30 | 840 | |
| 8 | Glass hole Cost for glass hole | 32 | nos | 31 | each | 31 | 992 | |
| 9 | Electrodes including electricity Electrodes with electricity: | 80 | nos | 10 | each | 10 | 800 | |
| 10 | Welder Welder / fabricator | 1 | nos | 700 | per day | 700 | 700 | |
| 11 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 1.5 | nos | 550 | per day | 550 | 825 | |
| 12 | Ordinary labour Ordinary labour | 2 | nos | 550 | per day | 550 | 1100 | |
| 14 | Skilled technician Skilled Technician | 0.25 | no | 1200 | per day | 1200 | 300 | |
| 15 | Semi skilled technician Semi skilled Technician | 0.5 | no | 800 | per day | 800 | 400 | |
| 16 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 17 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason Helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 18 | Welder Welder/fabricator | 0.25 | no | 700 | per day | 700 | 175 | |
| 19 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 20 | Workshop Charges 20.16 Work-shop charges: | 1 | - | 24709.7 | Unit | 1235.49 | 1235.49 | |
| 13 | Carrying of materials to work-shop and fabricated materials to site: | LS | 350 | |||||
| Sub-Total | 31320.09 | |||||||
| Contractor's Profit | 10% | 0.1 | 3132.01 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1096.2 | |||||
| Total | 35548.3 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2882.29 | ||||
| Grand Total | 38430.59 | |||||||
| Rate per sft | 844.64 | |||||||
| Rate per sqm | 9091.7 | |||||||