Breakup

20.17.1 Supplying, fitting and fixing verandah railing of standard height with 3mm thick 75mm x 50mm MS box for vertical post box @ 900 mm c/c fitting by welding on 150 mm x 100 mm x 6 mm anchor plate at base, base plate fitting with the floor by 50mm long royal bolt, 3mm thick 50mm x 38mm MS horizontal box fitting with the vertical post by welding @ 150 mm c/c including all other accessories and carrying, febrication, applying 2 (two) coats of synthetic enamel paint of approved quality over an anti-corrosive prime coat etc. complete in all respect for all floors and accepted by the Engineer-in-charge. (Exposed area of railing will be considered for measurement, rate is excluding the cost of painting).

Considering 1 No. of verandha railing Considering 13'-0" x 3'-6"= 45.50 sft. exposed surface

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 18/20/22 BWG MS Sheet/plate M.S. hollow box 3" x 2" x 1/8" @ 4.25 lbs. per rft. 7 x 3'-6"= 24.50 rft. Add wastage 5%= 1.23 rft. = 25.73 rft. = 109.35 Ibs. 109.35 lbs 77000 per M. ton 34.92 3818.5
2 18/20/22 BWG MS Sheet/plate 50mm x 38mm, 3mm thick square box @ 2.98 Ibs. per rft. 6 x 13'-3"= 79.50 rft. Add wastage 5%= 3.98 rft. = 83.48 rft. = 248.77 lbs. 248.77 lbs 77000 per M. ton 34.92 8687.05
3 18/20/22 BWG MS Sheet/plate 6" x 4" x 1/4" thick M.S. plate: @ 2.55 lbs per sft. 7 x 6" x 4"= 1.17 sft. Add wastage 5%= 0.06 sft. = 1.23 sft. = 3.14 Ibs. 3.14 lbs 77000 per M. ton 34.92 109.65
4 Electrodes including electricity Electrodes with electricity: 120 nos 10 each 10 1200
5 Royal bolt 2" Royal Bolt 20 nos 57 each 57 1140
6 Welder Welder / fabricator 1 no 700 per day 700 700
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 2 nos 550 per day 550 1100
8 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
10 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason Helper 0.5 no 550 per day 550 275
12 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
13 Welder Welder/fabricator 0.25 no 700 per day 700 175
14 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 0.5 no 550 per day 550 275
15 Workshop Charges 20.17.1 Work-shop charges: 1 - 18100.43 Unit 905.02 905.02
9 Carrying of materials to work-shop and fabricated materials to site: LS 245
Sub-Total 20180.22
Contractor's Profit 10% 0.1 2018.02
Contractor's Overhead Expenses 3.5% 0.035 706.31
Total 22904.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1857.12
Grand Total 24761.67
Rate per sft 544.22
Rate per sqm 5857.98
Help