Considering 10 steps Total rft of nosing: 10 x 3'-6"= 35 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mason / Mosaic mistry Cost of cutting @ 3 nos of grooves per steps for fixing 1.5" x 1.5" x 3.5" size clamps : Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 2 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 3 | Plain concrete (1:2:4) with brick chips Cost of CC (1:2:4) with smaller size of chips for fixing clamps: 30 x 1.5" x1.5" x3.5"= 0.14 cft | 0.14 | cft | 20151.67 | % cft | 201.52 | 28.21 | |
| 4 | M.S. angle, T and Z-section, Channel etc. Cost of 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft 10 x 3'-6"= 35.00 rft Add wastage 5%= 1.75 rft = 36.75 rft = 86.00 Ibs | 86 | lbs | 70000 | per M. ton | 31.75 | 2730.5 | |
| 5 | M.S. plain bar and F.I. bar (non-structural use) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft 10 x 3 x 3"= 7.50 rft Add wastage 5%= 0.38 rft = 7.88 rft = 2.52 Ibs | 2.52 | lbs | 70000 | per M. ton | 31.75 | 80.01 | |
| 6 | Cutting charge of MS angle Cutting charge of M.S. angle as per required measurement in/c cost of T & P. | 10 | nos | 10 | each | 10 | 100 | |
| 7 | Electrodes including electricity Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including bifercating on the other end. | 30 | nos | 10 | each | 10 | 300 | |
| 8 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 9 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 4163.72 | |||||||
| Contractor's Profit | 10% | 0.1 | 416.37 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 145.73 | |||||
| Total | 4725.82 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 383.17 | ||||
| Grand Total | 5108.99 | |||||||
| Rate per rft | 145.97 | |||||||
| Rate per rm | 478.93 | |||||||