20.18.6 Providing 32 mm x 32 mm x 6 mm S.S. angle to the nosing of steps of stair case

Considering 10 steps Total rft of nosing: 10 x 3'-6"= 35 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Cost of cutting @ 3 nos of grooves per steps for fixing 1.25" x 1.25" x 3.5" size clamps: Mason 0.25 no 700 per day 700 175
2 Skilled labour Skilled labour 0.5 no 600 per day 600 300
3 Plain concrete (1:2:4) with brick chips Cost of CC (1:2:4) with smaller size of chips for fixing clamps: 30 x 1.5" x1.5" x3.5"= 0.14 cft 0.14 cft 20151.67 % cft 201.52 28.21
4 30 mm x 30 mm x 6 mm SS angle Cost of 1.25" x 1.25" x 1/4" S.S. angle 10 x 3'-6"= 35.00 rft Add wastage 5%= 1.75 rft = 36.75 rft 36.75 rft 240 per foot 240 8820
5 M.S. plain bar and F.I. bar (non-structural use) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft 10 x 3 x 3"= 7.50 rft Add wastage 5%= 0.38 rft = 7.88 rft = 2.52 Ibs 2.52 lbs 70000 per M. ton 31.75 80.01
6 Cutting charge of MS angle Cutting charge of M.S. angle as per required measurement in/c cost of T & P. 10 nos 10 each 10 100
7 Electrodes including electricity Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including bifercating on the other end. 30 nos 10 each 10 300
8 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
9 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
Sub-Total 10253.22
Contractor's Profit 10% 0.1 1025.32
Contractor's Overhead Expenses 3.5% 0.035 358.86
Total 11637.4
Add VAT with adjustment factor. 1.08108 7.5% 0.075 943.57
Grand Total 12580.97
Rate per rft 359.46
Rate per rm 1179.39