Considering 1 no. of Column of 30"x20" Total length of angle :4x 3'-0"= 12.00 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. Cost of 2" x 2" x 3/16" M.S. angle for vertical: @ 2.432 Ibs per rft 4 x 3'-0"= 12.00 rft Add wastage 5%= 0.60 rft = 12.60 rft = 30.64 Ibs | 30.64 | lbs | 70000 | per M. ton | 31.75 | 972.82 | |
| 2 | M.S. plain bar and F.I. bar (non-structural use) Cost of 2" x 3/16" F.I. bar for bend: @ 1.28 Ibs per rft 1 x 8'-4"= 8.33 rft Add wastage 5%= 0.42 rft = 8.75 rft = 11.20 Ibs | 11.2 | lbs | 70000 | per M. ton | 31.75 | 355.6 | |
| 3 | Cutting charge of SS angle Cutting charge of M.S. angle as per required measurement in/c cost of T & P. | 4 | nos | 7.3 | each | 7.3 | 29.2 | |
| 4 | Mason / Mosaic mistry Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 5 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 6 | welding cost | LS | 70 | |||||
| Sub-Total | 1877.62 | |||||||
| Contractor's Profit | 10% | 0.1 | 187.76 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 65.72 | |||||
| Total | 2131.1 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 172.79 | ||||
| Grand Total | 2303.89 | |||||||
| Rate per rft | 192 | |||||||
| Rate per rm | 629.95 | |||||||