Breakup

21.1 Supplying, fitting and fixing MS grill fencing of any design and shape in boundary wall with 31 mm x 6 mm F.I. bar @ 150 mm c/c placed vertically after cutting as per required measurement. Welding the said F.I. bar with 2 nos. horizontal 30 mm x 6 mm F.I. bar placed one at top and another at bottom including embedding/fixing the horizontal F.I. bar in position with cutting grooves in wall up to 150 mm depth and mending good the damages with C.C. (1:2:4), finishing with two coats of painting with synthetic enamel paint over a coat of anti-corrosive paint etc. complete as per drawing and design and accepted by the Engineer-in-charge. (Rate is excluding the cost of painting)

Considering 1 No. of steel grill fencing Considering 8'-9" x 3'-1"= 26.98 sft grill work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. plain bar and F.I. bar (non-structural use) 1.25" x 1/4" F.I. bars: @ 1.06 lbs per rft Vertical: 17 x 3'-1"= 52.42 rft Horizontal: 2 x 9'-9"= 19.5 rft = 71.92 rft Add wastage 5%= 3.60 rft = 75.52 rft = 80.05 Ibs 80.05 lbs 70000 per M. ton 31.75 2541.59
2 Electrodes including electricity Electrodes in/c electricity 15 nos 10 each 10 150
3 Welder Welder / fabricator 0.5 no 700 per day 700 350
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 0.5 no 550 per day 550 275
5 Ordinary labour Ordinary labour 1 no 550 per day 550 550
7 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 3" x 3" x 6" size grooves 4 nos 550 per day 22.92 91.68
8 Plain concrete (1:2:4) with brick chips CC (1:2:4): 4 x 3" x 3" x 6"= 0.13 cft 0.13 cft 20151.67 % cft 201.52 26.2
9 Mason / Mosaic mistry Mason 0.3 no 700 per day 700 210
10 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.3 no 550 per day 550 165
11 Workshop Charges 21.1 Work-shop charges: 1 - 4066.27 Unit 203.31 203.31
6 Carrying of materials to work-shop and fabricated materials to site: LS 200
Sub-Total 4762.78
Contractor's Profit 10% 0.1 476.28
Contractor's Overhead Expenses 3.5% 0.035 166.7
Total 5405.76
Add VAT with adjustment factor. 1.08108 7.5% 0.075 438.3
Grand Total 5844.06
Rate per sft 216.6
Rate per sqm 2331.48
Help