Considering 1 No. of steel grill fencing Considering 8'-9" x 3'-1"= 26.98 sft grill work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. plain bar and F.I. bar (non-structural use) 1.25" x 1/4" F.I. bars: @ 1.06 lbs per rft Vertical: 17 x 3'-1"= 52.42 rft Horizontal: 2 x 9'-9"= 19.5 rft = 71.92 rft Add wastage 5%= 3.60 rft = 75.52 rft = 80.05 Ibs | 80.05 | lbs | 70000 | per M. ton | 31.75 | 2541.59 | |
| 2 | Electrodes including electricity Electrodes in/c electricity | 15 | nos | 10 | each | 10 | 150 | |
| 3 | Welder Welder / fabricator | 0.5 | no | 700 | per day | 700 | 350 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 7 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 3" x 3" x 6" size grooves | 4 | nos | 550 | per day | 22.92 | 91.68 | |
| 8 | Plain concrete (1:2:4) with brick chips CC (1:2:4): 4 x 3" x 3" x 6"= 0.13 cft | 0.13 | cft | 20151.67 | % cft | 201.52 | 26.2 | |
| 9 | Mason / Mosaic mistry Mason | 0.3 | no | 700 | per day | 700 | 210 | |
| 10 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper | 0.3 | no | 550 | per day | 550 | 165 | |
| 11 | Workshop Charges 21.1 Work-shop charges: | 1 | - | 4066.27 | Unit | 203.31 | 203.31 | |
| 6 | Carrying of materials to work-shop and fabricated materials to site: | LS | 200 | |||||
| Sub-Total | 4762.78 | |||||||
| Contractor's Profit | 10% | 0.1 | 476.28 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 166.7 | |||||
| Total | 5405.76 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 438.3 | ||||
| Grand Total | 5844.06 | |||||||
| Rate per sft | 216.6 | |||||||
| Rate per sqm | 2331.48 | |||||||