Breakup

21.2 Supplying, fitting and fixing MS grill fencing of any design and shape made with 19 mm x 19 mm x 3 mm box (box made with 2 nos.19 mm x 19 mm x 3 mm angle by continuous welding) placed vertically @ 150 mm c/c and welding the said vertical boxes with two Nos. horizontal 25 x 25 x 6 mm angle box (made with 2 Nos. 25 x 25 x 6 mm angle by welding), placing one at bottom and another at top and again fitting & fixing by welding the said horizontal tube box with 38 mm x 38 mm x 6 mm angle box vertical post made with 2 nos. 38 mm x 38 mm x 6 mm angle by welding) provided @ 1800 mm c/c including embedding the tube box post in brick R.C.C. pillar or core wall up to 375 mm depth after cutting grooves in wall/pillar including mending good the damages with C.C. (1:2:4) and finishing, curing, 2 coats of approved synthetic enamel paint over a coat of anti-corrosive paint etc. all complete as per design, drawing and accepted by the Engineer-in-charge. (Rate is excluding the cost of painting)

Considering 1 No. steel grill fencing Considering 2 panels: 12'-1.5" x 3'-0"= 36.38 sft fencing work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. angle, T and Z-section, Channel etc. 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs per rft @ 6'-0" c/c: 3 x 2 x 4'-6"= 27.00 rft Add wastage 5%= 1.35 rft = 28.35 rft = 66.34 Ibs 66.34 lbs 70000 per M. ton 31.75 2106.3
2 M.S. angle, T and Z-section, Channel etc. 1" x 1" x 1/4" M.S. angle box horizontally at top and bottom.: @ 1.49 lbs per rft 2 x 2 x 2 x 6'-0"= 48.00 rft Add wastage 5%= 2.40 rft = 50.40 rft = 75.10 lbs 75.1 lbs 70000 per M. ton 31.75 2384.42
3 M.S. angle, T and Z-section, Channel etc. 3/4" x 3/4" x 1/4" M.S. angle for box: @ 0.585 lbs per rft : 22 x 2 x 3'-0"= 132.00 rft Add wastage 5%= 6.60 rft = 138.60 rft = 81.08 lbs 81.08 lbs 70000 per M. ton 31.75 2574.29
4 Electrodes including electricity Electrodes in/c electricity 120 nos 10 each 10 1200
5 Welder Welder / fabricator 1.5 nos 700 per day 700 1050
6 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper 2 nos 550 per day 550 1100
7 Ordinary labour Ordinary labour 2 nos 550 per day 550 1100
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Labour charge for cutting 3" x 3" x 12" size grooves 4 nos 550 per day 45.83 183.32
10 Plain concrete (1:2:4) with brick chips CC (1:2:4): 4 x 3" x 3" x 12"= 0.25 cft 0.25 cft 20151.67 % cft 201.52 50.38
11 Mason / Mosaic mistry Mason 0.3 no 700 per day 700 210
12 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.3 no 550 per day 550 165
13 Workshop Charges 21.2 Work-shop charges: 1 - 11714.13 Unit 585.71 585.71
8 Carrying of materials to work-shop and fabricated materials to site: LS 200
Sub-Total 12909.42
Contractor's Profit 10% 0.1 1290.94
Contractor's Overhead Expenses 3.5% 0.035 451.83
Total 14652.19
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1188.01
Grand Total 15840.2
Rate per sft 435.4
Rate per sqm 4686.65
Help