Considering 1 No. steel grill fencing Considering a panel of 7'-9" x 3'-3"= 25.19 sft fencing work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft 2 x 3'-3"= 6.50 rft Horizontal: 2 x 7'-9"= 15.50 rft = 22 rft Add wastage 5%= 1.1 rft 23.1 rft = 54.05 Ibs | 54.05 | lbs | 70000 | per M. ton | 31.75 | 1716.09 | |
| 2 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 3/8" dia M.S. rod: @ 0.167 lbs per rft 20 x 3'-3"= 65.00 rft 8 x 7'-9"= 62.00 rft 127.00 rft Add wastage 5%= 6.35 rft = 133.35 rft = 22.27 lbs | 22.27 | lbs | 65000 | per M. ton | 29.48 | 656.52 | |
| 3 | Electrodes including electricity Electrodes in/c electricity | 30 | nos | 10 | each | 10 | 300 | |
| 4 | Welder Welder / fabricator | 0.5 | no | 700 | per day | 700 | 350 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.5 | no | 550 | per day | 550 | 275 | |
| 6 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 7 | Ordinary labour Carrying of materials to work-shop and fabricated materials to site: | 1 | LS | 550 | per day | 401.5 | 401.5 | |
| 8 | Welder Welder / fabricator | 0.3 | no | 700 | per day | 700 | 210 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Welder helper | 0.3 | no | 550 | per day | 550 | 165 | |
| 10 | Workshop Charges 21.3 Work-shop charges: | 1 | - | 4248.86 | Unit | 212.44 | 212.44 | |
| Sub-Total | 4836.55 | |||||||
| Contractor's Profit | 10% | 0.1 | 483.66 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 169.28 | |||||
| Total | 5489.49 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 445.09 | ||||
| Grand Total | 5934.58 | |||||||
| Rate per sft | 235.61 | |||||||
| Rate per sqm | 2536.11 | |||||||