Breakup

04.1 Brick works with first class bricks with cement sand (F.M. 1.2) mortar (1:6) in foundation and plinth, filling the joints/interstices fully with mortar, racking out the joints, cleaning and soaking the bricks at least for 24 hours before use and curing at least for 7 days etc. all complete including cost of water, electricity and other charges and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M)

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 1100 nos 10000 per % 0 nos 10 11000
2 Sand (F.M. 1.2) Sand (F.M 1.2) in/c wastage 28 cft 1900 per % cft 19 532
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 4.4 bags 410 per bag 410 1804
4 Head mason / Mosaic head mistry Head mason 0.1 nos 800 per day 800 80
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Skilled labour Skilled labour 1 no 600 per day 600 600
7 Ordinary labour Ordinary labour 1.5 no 550 per day 550 825
8 Ordinary labour Labour for soaking & cleaning bricks 2 nos 550 per day 550 1100
9 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day 0.875 nos 550 per day 550 481.25
10 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 275 275
Sub-Total 17397.25
Contractor's Profit 10% 0.1 1739.73
Contractor's Overhead Expenses 3.5% 0.035 608.9
Total 19745.88
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1601.02
Grand Total 21346.9
Rate per cft 213.47
Rate per per cumsqm 7538.69