Breakup

21.11.2 Manufacturing, supplying, fitting and fixing S.S. grill fencing(Grade 201) as per design in boundary wall with 50mm x 50mm x1.5mm box horizontal section for top & bottom part & 25mmx1.5mm ss round horizontal section @ 4" c/c between top & bottom which are attached with 4 mm thichness ss base plate of required size & ss royal bolt with side column/wall, 37 mm x 1.5 mm ss round vertical section 3'-0" c/c section attched with bottom RCC section and top SS vertical section with required welding, mending good the damages with concrete(1:2:4) required polishing, finishing etc. all complete as per drawing and accepted by the Engineer-in-charge.

Considering 1 No. SS grill fencing Considering 01 panel:10'-0" x 4'-6"= 45 sft fencing work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm x 50 mm x 1.5 mm SS box (grade A201) 50 mm x 50 mm x 1.5 mm ss box section as horizontal section for top & bottom part 2x10'-0"= 20.0 rft Add wastage 5%= 1 rft = 21.00 rft 21 rft 300 per foot 300 6300
2 25 mm dia stainless steel (2 mm thick) pipe-(grade A201) 25mm x 1.5 mm ss round section as horizontal section between top & bottom @ 4'' c/c 12x10'-0"= 120.00 rft Add wastage 5%= 6.00 rft = 126.00 rft 126 rft 109 per foot 109 13734
3 37 mm dia stainless steel (1.5 mm thick) pipe-(grade A201) 37mm x 1.5 mm ss round section as vertical section 3'-0" c/c 3x4'-6"= 13.50 rft Add wastage 5%= 0.68 rft = 14.18 rft 14.18 rft 138 per foot 138 1956.84
4 4mm thick SS base plate 4mm thickness SS base plate= 18.00 kg 18 kg 250 per kg 250 4500
5 Solid SS royal bolt with cap Solid SS royal bolt with cap= 16.00 nos 16 nos 40 each 40 640
6 Electrodes including electricity Electrodes in/c electricity 150 nos 10 each 10 1500
7 Welder Welder / fabricator 0.5 nos 700 per day 700 350
9 Ordinary labour Ordinary labour 0.75 nos 550 per day 550 412.5
11 Ordinary labour Labour charge for cutting 3" x 3" x 12" size grooves 3 nos 550 per day 27.5 82.5
12 Plain concrete (1:2:4) with brick chips CC (1:2:4): 3 x 3" x 3" x 12"= 0.19 cft 0.19 cft 20151.67 % cft 201.52 38.29
13 Mason / Mosaic mistry Mason 0.3 nos 700 per day 700 210
14 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.3 nos 550 per day 550 165
14 Skilled labour Welder helper 0.75 nos 600 per day 600 450
15 Work-shop charges & polishing charge 21.11.2 Work-shop & polishing charges: 1 - 30043.34 Unit 1502.17 1502.17
10 Carrying of materials to work-shop and fabricated materials to site: LS 200
Sub-Total 32041.3
Contractor's Profit 10% 0.1 3204.13
Contractor's Overhead Expenses 3.5% 0.035 1121.45
Total 36366.88
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2948.66
Grand Total 39315.54
Rate per sft 873.69
Rate per sqm 9404.4
Help