Breakup

21.12 Supplying, fitting and fixing fency grill in Boundary wall made of 38 mm x 38 mm x 6 mm M.S. tube vertical section @ 150 mm c/c and 19 mm x 19 mm x 3 mm M.S. Tube horizontal section @ 900 mm c/c fabricating, welding in each point , including cost of electricity, tools and plants, workshop charges, carriage of the same including cutting groves in the R.C.C. or brick work, mending good the damages with C.C. (1:2:4) etc, all complete for all floors accepted by the Engineer-in-charge. (Rate is excluding the cost of painting)

Considering 1 No. steel grill fencing Considering 1 panels: 10' x 7'-0"= 70 sft fencing work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. angle, T and Z-section, Channel etc. 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs per rft @ 6" c/c: 21x 7= 147.00 rft Add wastage 5%= 7.35 rft = 154.35 rft = 361.18 Ibs 361.18 lbs 70000 per M. ton 31.75 11467.47
2 M.S. angle, T and Z-section, Channel etc. 3/4" x 3/4" x 1/4" M.S. angle for box: @ 0.585 lbs per rft : 2 x 10'-0"= 20.00 rft Add wastage 5%= 1.00 rft = 21.00 rft = 12.29 lbs 12.29 lbs 70000 per M. ton 31.75 390.21
3 Electrodes including electricity Electrodes in/c electricity 50 nos 10 each 10 500
4 Welder Welder / fabricator 0.5 nos 700 per day 700 350
5 Skilled labour Welder helper 0.5 nos 600 per day 600 300
6 Ordinary labour Ordinary labour 1 nos 550 per day 550 550
8 Ordinary labour Labour charge for cutting 3" x 3" x 12" size grooves 4 nos 550 per day 27.5 110
9 Plain concrete (1:2:4) with brick chips CC (1:2:4): 4 x 3" x 3" x 12"= 0.25 cft 0.25 cft 20151.67 % cft 201.52 50.38
10 Mason / Mosaic mistry Mason 0.5 no 700 per day 700 350
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.5 no 550 per day 550 275
12 Work-shop charges 21.12 Work-shop charges: 1 - 14106.19 Unit 705.31 705.31
7 Carrying of materials to work-shop and fabricated materials to site: LS 550
Sub-Total 15598.37
Contractor's Profit 10% 0.1 1559.84
Contractor's Overhead Expenses 3.5% 0.035 545.94
Total 17704.15
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1435.47
Grand Total 19139.62
Rate per sft 273.43
Rate per sqm 2943.2
Help