Breakup

04.2 Brick works of width one brick or one and a half brick length of first class bricks with cement sand (F.M. 1.2) mortar (1:6) in superstructure including raking out joints, filling the interstices with mortar, cleaning and soaking the bricks at least for 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete (measurement to given as 250 mm width for one brick length and 375 mm for one brick and a half brick length) and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 1100 nos 10000 per % 0 nos 10 11000
2 Sand (F.M. 1.2) Sand (F.M 1.2) in/c wastage 28 cft 1900 per % cft 19 532
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 4.4 bags 410 per bag 410 1804
4 Head mason / Mosaic head mistry Head mason 0.1 nos 800 per day 800 80
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Skilled labour Skilled labour 1 no 600 per day 600 600
7 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
8 Ordinary labour Labour for soaking & cleaning bricks 2 nos 550 per day 550 1100
9 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day: 0.875 no 550 per day 550 481.25
10 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 275 275
11 Scaffolding Scaffolding 25 sft 10 per sft 10 250
12 Ordinary labour Extra labour for carriage 1 no 550 per day 550 550
13 Ordinary labour Extra labour for 7 days curing 0.25 no 550 per day 550 137.5
14 Ordinary labour Labour for screening & washing sand 1 no 550 per day 550 550
Sub-Total 18884.75
Contractor's Profit 10% 0.1 1888.48
Contractor's Overhead Expenses 3.5% 0.035 660.97
Total 21434.2
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1737.91
Grand Total 23172.11
Rate per cft 231.72
Rate per per cumsqm 8183.19