Breakup

21.14.1 600 mm circular dia

Considering 10 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 SS rod (grade A201 ) 10 mm SS Rod (@ 0.62 kg/m) 6 x 10'-0" = 60.00 rft 5 x 6.28' = 31.40 rft = 91.40 rft Add wastage 5% = 4.57 rft = 95.97 rft = 29.25 rm = 26.33 kg 26.33 kg 300 per kg 300 7899
2 SS galvanized barbed wire (dia 2.5 mm) Barbed wire works: @0.15kg/m 31x 6'-4" = 253.2 rft Add wastage 5% = 12.66 rft = 265.86 rft = 81.03 rm = 12.15 kg 12.15 kg 800 per kg 800 9720
3 38 mm x 38 mm x 6 mm SS angle (grade A201 ) 38 mm x 38 mm x 6 mm Angle (@ 3.3 kg/m) 3 x 5'-9" = 17.25 rft Add wastage 5% = 0.86 rft = 18.11 rft = 5.52 rm = 18.22 kg 18.22 kg 310 per foot 310 5648.2
4 Electrodes including electricity Electrodes 20 nos 10 each 10 200
5 Welder Welder / fabricator 0.5 nos 700 per day 700 350
6 Skilled labour Helper 0.5 nos 600 per day 600 300
8 Ordinary labour Making holes 3 nos 550 per day 22 66
9 Plain concrete (1:2:4) with brick chips Plain concrete: (1:2:4) 3x3"X3"x9" = 0.14 cft 0.14 cft 20151.67 % cft 201.52 28.21
10 Mason / Mosaic mistry Mason 0.25 nos 700 per day 700 175
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.25 nos 550 per day 550 137.5
12 Ordinary labour Ordinary labour 0.5 nos 550 per day 550 275
13 Work-shop charges & polishing charge 21.14.1 Work-shop & polishing charges 1 - 24217.2 Unit 1210.86 1210.86
7 Carrying materials to workshop & to site LS 100
Sub-Total 26109.77
Contractor's Profit 10% 0.1 2610.98
Contractor's Overhead Expenses 3.5% 0.035 913.84
Total 29634.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2402.8
Grand Total 32037.39
Rate per rft 3203.7
Rate per rm 10511.34
Help