Breakup

21.15 Manufacturing, supplying, fitting and fixing steel grill fencing in boundary wall with 38 mm dia MS Pipe with thickness 6 mm placed @ 150 mm c/c vertically and mending good the damages with C.C. (1:2:4), finishing with two coats of painting with synthetic enamel paint over a coat of anti-corrosive paint etc. complete as per drawing and design and accepted by the Engineer-in-charge. (Rate is excluding the cost of painting)

Considering 1 No. of steel grill fencing Considering 10'-0" x 5'-0"= 50 sft work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. angle, T and Z-section, Channel etc. 1.5" x 1/4" MS Pipe: @ 3.34 lbs per rft Vertical: 21 x 5'-0"= 105 rft Add wastage 5%= 5.25 rft = 110.25 rft = 368.24 Ibs 368.24 lbs 70000 per M. ton 31.75 11691.62
2 Electrodes including electricity Electrodes in/c electricity 100 nos 10 each 10 1000
3 Welder Welder / fabricator 0.75 no 700 per day 700 525
4 Skilled labour Welder helper 0.75 no 600 per day 600 450
5 Ordinary labour Ordinary labour 1 no 550 per day 550 550
7 Ordinary labour Labour charge for cutting 3" x 3" x 6" size grooves 25 nos 550 per day 22 550
8 Plain concrete (1:2:4) with brick chips CC (1:2:4): 25 x 3.14 x 1.5x1.5= 1.22 cft 1.22 cft 20151.67 % cft 201.52 245.85
9 Mason / Mosaic mistry Mason 0.3 no 700 per day 700 210
10 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason helper 0.3 no 550 per day 550 165
11 Work-shop charges 21.15 Work-shop charges: 1 - 14490.16 Unit 724.51 724.51
6 Carrying of materials to work-shop and fabricated materials to site: LS 275
Sub-Total 16386.98
Contractor's Profit 10% 0.1 1638.7
Contractor's Overhead Expenses 3.5% 0.035 573.54
Total 18599.22
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1508.04
Grand Total 20107.26
Rate per sft 402.14
Rate per sqm 4328.63
Help