Considering 10 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Garjan/Jam/local Sal 1/2"x1/2"size wooden bit (garjan wood):(10'-0"x0.5"x0.5"=0.02cft + Add wastage 10%=0.002cft)=0.022cft | 0.022 | cft | 2200 | per cft | 2200 | 48.4 | |
| 2 | Nails and wires Cost of nails | 1 | LS | 70 | per kg | 7 | 7 | |
| 3 | Carpenter Labour charge for fitting and fixing Carpenter | 0.2 | no | 700 | per day | 700 | 140 | |
| Sub-Total | 195.4 | |||||||
| Contractor's Profit | 10% | 0.1 | 19.54 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 6.84 | |||||
| Total | 221.78 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 17.98 | ||||
| Grand Total | 239.76 | |||||||
| Rate per rft | 24 | |||||||
| Rate per rm | 78.74 | |||||||