22.1 Supplying, fitting and fixing of wooden wedge (12 mm base x 12 mm height) instead of putty for fixing glass panes with wooden frame by nails or by any other approved method including the cost of necessary wood (Garjan/ Jam/ Local sal), nails etc. all complete and accepted by the Engineer-in-charge. ( Rate is excluding the cost of wooden frame, painting and 5 mm thick glass panes)

Considering 10 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Garjan/Jam/local Sal 1/2"x1/2"size wooden bit (garjan wood):(10'-0"x0.5"x0.5"=0.02cft + Add wastage 10%=0.002cft)=0.022cft 0.022 cft 2200 per cft 2200 48.4
2 Nails and wires Cost of nails 1 LS 70 per kg 7 7
3 Carpenter Labour charge for fitting and fixing Carpenter 0.2 no 700 per day 700 140
Sub-Total 195.4
Contractor's Profit 10% 0.1 19.54
Contractor's Overhead Expenses 3.5% 0.035 6.84
Total 221.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 17.98
Grand Total 239.76
Rate per rft 24
Rate per rm 78.74