Breakup

22.2.2 25 mm dia Aluminium pipe curtain rail

Considering : 6'-0" = 6.00 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 25 mm Aluminium pipe Cost of pipe: 25 mm Aluminium pipe Horizontal 1 x 6'-0"= 6.00 rft Add wastage 5%= 0.30 rft = 6.30 rft 6.3 rft 140 per foot 140 882
2 Clamp Cost of best quality SS clamps 3 nos 40 each 40 120
4 Carpenter Carpenter 0.0625 no 700 per day 700 43.75
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 0.0625 no 550 per day 550 34.38
3 Rowel plug, screws etc. LS 80
6 Carrying Cost, Electricity,tools & plant, Sundries etc. LS 20
Sub-Total 1180.13
Contractor's Profit 10% 0.1 118.01
Contractor's Overhead Expenses 3.5% 0.035 41.3
Total 1339.44
Add VAT with adjustment factor. 1.08108 7.5% 0.075 108.6
Grand Total 1448.04
Rate per rft 241.33
Rate per rm 791.8