Considering : 6'-0" = 6.00 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 20 mm dia stainless steel (1 mm thick) pipe Cost of pipe: 20 mm dia SS pipe Horizontal 1 x 6'-0"= 6.00 rft Add wastage 5%= 0.30 rft = 6.30 rft | 6.3 | rft | 70 | per foot | 70 | 441 | |
| 2 | Clamp Cost of best quality SS clamps | 3 | nos | 40 | each | 40 | 120 | |
| 4 | Carpenter Carpenter | 0.0625 | no | 700 | per day | 700 | 43.75 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.0625 | no | 550 | per day | 550 | 34.38 | |
| 3 | 2 sets Rowel plug, screws etc. | LS | 180 | |||||
| 6 | Carrying Cost, Electricity,tools & plant, Sundries etc. | LS | 20 | |||||
| Sub-Total | 839.13 | |||||||
| Contractor's Profit | 10% | 0.1 | 83.91 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 29.37 | |||||
| Total | 952.41 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 77.22 | ||||
| Grand Total | 1029.63 | |||||||
| Rate per rft | 171.67 | |||||||
| Rate per rm | 563.25 | |||||||