Considering : 6'-0" = 6.00 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia stainless steel (1.2 mm thick) pipe Cost of pipe: 20 mm dia SS pipe Horizontal 1 x 6'-0"= 6.00 rft Add wastage 5%= 0.30 rft = 6.30 rft | 6.3 | rft | 100 | per foot | 100 | 630 | |
| 2 | Clamp Cost of best quality SS clamps | 3 | nos | 40 | each | 40 | 120 | |
| 4 | Carpenter Carpenter | 0.0625 | no | 700 | per day | 700 | 43.75 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.0625 | no | 550 | per day | 550 | 34.38 | |
| 3 | Rowel plug, screws etc. | LS | 180 | |||||
| 6 | Carrying Cost, Electricity,tools & plant, Sundries etc. | LS | 20 | |||||
| Sub-Total | 1028.13 | |||||||
| Contractor's Profit | 10% | 0.1 | 102.81 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 35.98 | |||||
| Total | 1166.92 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 94.62 | ||||
| Grand Total | 1261.54 | |||||||
| Rate per rft | 210.33 | |||||||
| Rate per rm | 690.09 | |||||||