04.3 Brick works with first class bricks with cement sand (F.M. 1.2) mortar (1:4) in exterior walls including filling the interstices with mortar, raking out joints, cleaning and socking the bricks at least for 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete including cost of water, electricity and other charges (measurement to given as 250 mm width for one brick length and 375 mm for one brick and a half brick length) accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) In ground floor

Considering 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 1st class/Picked jhama standard bricks Bricks 1100 nos 10000 per % 0 nos 10 11000
2 Sand (F.M. 1.2) Sand (F.M 1.2) in/c wastage 31 cft 1900 per % cft 19 589
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 6 bags 410 per bag 410 2460
4 Head mason / Mosaic head mistry Head mason 0.1 no 800 per day 800 80
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Skilled labour Skilled labour 1 no 600 per day 600 600
7 Ordinary labour Ordinary labour 2.5 no 550 per day 550 1375
8 Ordinary labour Labour for soaking & cleaning bricks 2 no 550 per day 550 1100
9 Ordinary labour Screening and washing sand 1 no 550 per day 550 550
10 Ordinary labour Labour for 7 days curing '@ 1/8 labour per day: 0.875 nos 550 per day 550 481.25
11 Scaffolding Scaffolding 25 sft 10 per sft 10 250
12 Ordinary labour Local carriage, sundries, T & P etc. 1 LS 550 per day 275 275
Sub-Total 19460.25
Contractor's Profit 10% 0.1 1946.03
Contractor's Overhead Expenses 3.5% 0.035 681.11
Total 22087.39
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1790.87
Grand Total 23878.26
Rate per cft 238.78
Rate per per cumsqm 8432.52