Breakup

22.6 Supplying, fitting and fixing of Chattogram Teak wood strip (62 mm x 25 mm x 20 mm) for fixing of aluminium curtain rails as per design and drawing, fitting and fixing coat of priming etc. all complete and accepted by the Engineer-in-charge.(Rate is excluding the cost of polishing etc.)

Considering 4 rft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak (a)Chattogram Teak wood:(1x4'-0"x2.5"x1"=0.069cft + Add wastage 5%=0.0035cft)=0.073cft 0.073 cft 4400 per cft 4400 321.2
2 Carpenter Labour charge : Carpenter 0.0833333 no 700 per day 700 58.33
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper 0.25 no 550 per day 550 137.5
4 Ordinary labour Fitting, fixing, screws and polishing 1 LS 550 per day 275 275
Sub-Total 792.03
Contractor's Profit 10% 0.1 79.2
Contractor's Overhead Expenses 3.5% 0.035 27.72
Total 898.95
Add VAT with adjustment factor. 1.08108 7.5% 0.075 72.89
Grand Total 971.84
Rate per rft 243
Rate per rm 797283