Considering 4 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak (a)Chattogram Teak wood:(1x4'-0"x2.5"x1"=0.069cft + Add wastage 5%=0.0035cft)=0.073cft | 0.073 | cft | 4400 | per cft | 4400 | 321.2 | |
| 2 | Carpenter Labour charge : Carpenter | 0.0833333 | no | 700 | per day | 700 | 58.33 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 4 | Ordinary labour Fitting, fixing, screws and polishing | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 792.03 | |||||||
| Contractor's Profit | 10% | 0.1 | 79.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 27.72 | |||||
| Total | 898.95 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 72.89 | ||||
| Grand Total | 971.84 | |||||||
| Rate per rft | 243 | |||||||
| Rate per rm | 797283 | |||||||