Breakup

22.14.1 With partition of uPVC hollow section

Considering 1 No. partition of 6 sqm : (size 2m X 3m)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 T-frame T-frame 9 rm 145 per meter 145 1305
2 L-frame L-frame 10 rm 145 per meter 145 1450
3 Hollow bit Hollow bit 28 rm 64 per meter 64 1792
4 T-inner joint clamp T-inner joint clamp 14 pcs 10 each 10 140
5 L-inner joint clamp L-inner joint clamp 4 pcs 14.5 each 14.5 58
6 Rivets (normal) Rivet 80 pcs 2 each 2 160
7 Screw for hollow partition Screw 24 pcs 2.3 each 2.3 55.2
8 Rowel plug Rowel plug 24 pcs 1 each 1 24
9 uPVC hollow section wall thickness 2.5 mm Hollow section 6 sqm 950 per meter 950 5700
10 Carpenter Carpenter 1 no 700 per day 700 700
11 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpentr helper 2 no 550 per day 550 1100
12 Ordinary labour Carrying charge 1 LS 550 per day 275 275
Sub-Total 12759.2
Contractor's Profit 10% 0.1 1275.92
Contractor's Overhead Expenses 3.5% 0.035 446.57
Total 14481.69
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1174.19
Grand Total 15655.88
Rate per sqm 2609.33
Rate per sqm 2609.33