Considering 1 No. partition of 6 sqm : (size 2m X 3m)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | T-frame T-frame | 9 | rm | 145 | per meter | 145 | 1305 | |
| 2 | L-frame L-frame | 10 | rm | 145 | per meter | 145 | 1450 | |
| 3 | Hollow bit Hollow bit | 28 | rm | 64 | per meter | 64 | 1792 | |
| 4 | T-inner joint clamp T-inner joint clamp | 14 | pcs | 10 | each | 10 | 140 | |
| 5 | L-inner joint clamp L-inner joint clamp | 4 | pcs | 14.5 | each | 14.5 | 58 | |
| 6 | Rivets (normal) Rivet | 80 | pcs | 2 | each | 2 | 160 | |
| 7 | Screw for hollow partition Screw | 24 | pcs | 2.3 | each | 2.3 | 55.2 | |
| 8 | Rowel plug Rowel plug | 24 | pcs | 1 | each | 1 | 24 | |
| 9 | uPVC hollow section wall thickness 2.5 mm Hollow section | 6 | sqm | 950 | per meter | 950 | 5700 | |
| 10 | Carpenter Carpenter | 1 | no | 700 | per day | 700 | 700 | |
| 11 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpentr helper | 2 | no | 550 | per day | 550 | 1100 | |
| 12 | Ordinary labour Carrying charge | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 12759.2 | |||||||
| Contractor's Profit | 10% | 0.1 | 1275.92 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 446.57 | |||||
| Total | 14481.69 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1174.19 | ||||
| Grand Total | 15655.88 | |||||||
| Rate per sqm | 2609.33 | |||||||
| Rate per sqm | 2609.33 | |||||||