Breakup

22.14.2 With 5 mm glass

Considering 1 No. partition of 6 sqm :(size 2m X 3m)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 T-frame T-frame 9 rm 145 per meter 145 1305
2 L-frame L-frame 10 rm 145 per meter 145 1450
3 Hollow bit Glass bit 28 rm 64 per meter 64 1792
4 Round rubber bit Round rubber bit 14 rm 23 per meter 23 322
5 Rubber bit Rubber bit 4 rm 11.21 per meter 11.21 44.84
6 T-inner joint clamp T-inner joint clamp 80 pcs 10 each 10 800
7 L-inner joint clamp L-inner joint clamp 24 pcs 14.5 each 14.5 348
8 Rivets (normal) Rivet 24 pcs 2 each 2 48
9 Screw for hollow partition Screw 6 pcs 2.3 each 2.3 13.8
10 Rowel plug Rowel plug 4.5 pcs 1 each 1 4.5
11 Adhesive Adhesive 1.5 kg 222 per kg 222 333
12 5 mm clear glass 5 mm glass 64.56 sft 77 per sft 77 4971.12
13 Carpenter Carpenter 1 nos 700 per day 700 700
14 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 2 nos 550 per day 550 1100
15 Ordinary labour Carrying charge 1 LS 550 per day 275 275
Sub-Total 13507.26
Contractor's Profit 10% 0.1 1350.73
Contractor's Overhead Expenses 3.5% 0.035 472.75
Total 15330.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1243.03
Grand Total 16573.77
Rate per sqm 2762.33
Rate per sqm 2762.33
Help