Considering 1 No. partition of 6 sqm :(size 2m X 3m)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | T-frame T-frame | 9 | rm | 145 | per meter | 145 | 1305 | |
| 2 | L-frame L-frame | 10 | rm | 145 | per meter | 145 | 1450 | |
| 3 | Hollow bit Glass bit | 28 | rm | 64 | per meter | 64 | 1792 | |
| 4 | Round rubber bit Round rubber bit | 14 | rm | 23 | per meter | 23 | 322 | |
| 5 | Rubber bit Rubber bit | 4 | rm | 11.21 | per meter | 11.21 | 44.84 | |
| 6 | T-inner joint clamp T-inner joint clamp | 80 | pcs | 10 | each | 10 | 800 | |
| 7 | L-inner joint clamp L-inner joint clamp | 24 | pcs | 14.5 | each | 14.5 | 348 | |
| 8 | Rivets (normal) Rivet | 24 | pcs | 2 | each | 2 | 48 | |
| 9 | Screw for hollow partition Screw | 6 | pcs | 2.3 | each | 2.3 | 13.8 | |
| 10 | Rowel plug Rowel plug | 4.5 | pcs | 1 | each | 1 | 4.5 | |
| 11 | Adhesive Adhesive | 1.5 | kg | 222 | per kg | 222 | 333 | |
| 12 | 5 mm clear glass 5 mm glass | 64.56 | sft | 77 | per sft | 77 | 4971.12 | |
| 13 | Carpenter Carpenter | 1 | nos | 700 | per day | 700 | 700 | |
| 14 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 2 | nos | 550 | per day | 550 | 1100 | |
| 15 | Ordinary labour Carrying charge | 1 | LS | 550 | per day | 275 | 275 | |
| Sub-Total | 13507.26 | |||||||
| Contractor's Profit | 10% | 0.1 | 1350.73 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 472.75 | |||||
| Total | 15330.74 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1243.03 | ||||
| Grand Total | 16573.77 | |||||||
| Rate per sqm | 2762.33 | |||||||
| Rate per sqm | 2762.33 | |||||||